Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 06/18/2001 |
PLUMBING - FINAL |
|
Approved |
S.T.0.I CORRECTIONS MADE. |
| 06/14/2001 |
PLUMBING - FINAL |
|
Partial Approval |
IVRS - Inspection 0000*PLEASE NOTE NO GAS TO BUILDING .PLEASE PROVIDE 1" AIR GAP ON CONDINSET ANDF RELIEF LINES TO FLOOR SINK.ALL CO TO GRADE. |
| 05/18/2001 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection 0000*1)CUT CO TO GRADE INSTALL VACUUM BREAKERS.CAULK ALL FIXTURES.FINISH/CONDINSATE LINES.INSTALL TRAP PRIMERS.INSTALL WATER METER AND VALUES.ANCHOR DISHWATER DISCHARGER LINE.PROVIDE APPROVED STRAP FOR EXPANSION TANK PROVIDE LADDER FOR ROOF. |
| 04/05/2001 |
PLUMBING - FINAL |
|
Not ready for Inspection |
INFO REQUEST: COY, COUYLD YOU CONTACT THE CONTRACTOR RESPONSIBLE FOR INSTALLING THE BACK WATER VALVES BETWEEN BLDG DRAIN AND SEWER TO PLEASE INSTALL VALVES PER PLAN |