Permit: T00CM02265

Parcel: 140292130


Addresses:

3535 E VALENCIA RD


Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Permit Number - T00CM02265

Inspection Description - PLUMBING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
04/05/2001 PLUMBING - INTERMEDIATE Approved IVRS - Inspection 0000*
03/01/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000* ADDED ROOF DRAIN S.W. CORNER. I WILL CHECK ON REVISED PLANS
02/23/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000* 1) 1ST FLOOR S. W. DOUBLE BATHROOM N/H DWV OK WATER TEST OK 2) COPPER OK PRESSURE TEST OK 3) OK TO COVER WALLS
02/22/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000* 1) S.E. BATHROOM 2ND FLOOR 2) N/H DWV OK WATER TEST OK 3) COPPER OK PRESSURE TEST OK 4) OK TO COVER WALLS
5) FLOOR DRAINS OK
02/16/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000* 1) NORTH WEST SECOND FLOOR BATHROOMS DWV OK WATER TEST OK
2) COPPER OK PRESSURE TEST OK 3) 2ND FLOOR 4 BLDG DRAIN OK TO TIE-IN AT BLDG SEWER
02/08/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000*
WATER HCS
BLDG WATER SUPPLY 4" COPPER AT BLDG TRANSITION WITH FLANGE TO C 900 PVC UNDERGROUND THEN BACK TO COPPER AT METER
NEED TO SEE TIE IN AT METER
PRESSURE TEST TO 150# OK
OK TO COVER
BACKWATER VALVE PIT AND COVER OK
EAST WING BATHROOMS FIRST FLOOR N/H OK WATER TEST OK COPPER OK PRESSURE TEST OK
OK TO COVER FIRST FLOOR WALLS ONLY
02/07/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000*
ROOF DRAINS, 14 SETS, DRAINS AND OVERFLOWS OK
WATER TEST OK
OK TO COVER WHERE APPLICABLE
OVERFLOW SCUPPERS OK
NEED TO SEE ROOF DRAIN EXTENSION, PAST BLDG
02/05/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000* 1) 4TH FLOOR DRAINS IN BATHROOMS OK. OK TO COVER. 2) JANITORS SINK NORTH WING OK
01/26/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000*
FIRST FLOOR NORTH WING BATHROOMS OK
DWV N/H OK WATER TEST OK
COPPER OK PRESSURE TEST OK
T&P DRAIN OK TRAP PRIMES OK
RECIRC LINE OUT OF BATHROOM OK
OK TO COVER WALLS
01/25/2001 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection 0000*
NORTH WING 1ST FLOOR BATHROOM OK TO COVER ONE SIDE