Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 12/20/2001 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 12/12/2001 |
FRAMING |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) DOG LOOSE INSDIE ADDITION COULDN'T DO INTERMEDIATE INSPECTION JUST THE GAS YARD LINE, 2ND STOP SAME DAY 1) HANGER AT GLU LAM A. HANGER AT SOUTH SIDE REQUIRED A 10D HANGER NAIL B. HUS 26 HANGER AT NORTH SIDE REQUIRES A 16D HANGER NAIL 2) NEW OUTLET AT KITCHEN TO BE ON A SPERATE CIRCUIT 3) WILL NEED A GAS PRESSURE TEST ON NEW BLACK IRON PIPE TO ROOF UNIT |
| 05/22/2001 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*/ 1) CANNOT APPROVE FRAMING UNTIL ALL TRADES ARE COMPLETE |
| 05/18/2001 |
FRAMING |
|
Denied |
|