Date Description Inspector Results Comments
06/23/2026 Reconnect Only: Electrical Clearance Not Ready please label the pedestal with a metallic riveted label with the proper space number. The panel is identified with black marker, which is not acceptable. The permit identifies unit 65 but the actual pedestal is 64 please correct prior to requesting inspection again
06/26/2026 Reconnect Only: Electrical Clearance Not Ready Permit is for phase 65 pedestal is not marked properly. It has a marker that says 64 please label the pedestal with a metallic label and correct the address issue.
07/01/2026 Reconnect Only: Electrical Clearance Passed