Inspection Status: Not Ready
Inspection History: Reconnect Only: Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2026 |
Reconnect Only: Electrical Clearance |
|
Not Ready |
please label the pedestal with a metallic riveted label with the proper space number. The panel is identified with black marker, which is not acceptable. The permit identifies unit 65 but the actual pedestal is 64 please correct prior to requesting inspection again |
| 06/26/2026 |
Reconnect Only: Electrical Clearance |
|
Not Ready |
Permit is for phase 65 pedestal is not marked properly. It has a marker that says 64 please label the pedestal with a metallic label and correct the address issue. |
| 07/01/2026 |
Reconnect Only: Electrical Clearance |
|
Passed |
|