Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case: S99-061

Parcel: 13708001B


Addresses:

135 W NEBRASKA ST


Inspection Status: Passed

Inspection History: COT - ENGR - Site - Assurance Release

Plan Number - S99-061

Inspection Description - COT - ENGR - Site - Assurance Release

Inspection Status - Passed

Date Description Inspector Results Comments
06/04/2001 COT - ENGR - Site - Assurance Release MBERGHUI APPR Entered by MKALTHOF -
06/30/2000 COT - ENGR - Site - Assurance Release Passed
07/11/2000 COT - ENGR - Site - Assurance Release EABRIGO APPR Entered by FRODRIGU -
07/12/2000 COT - ENGR - Site - Assurance Release Passed
10/17/2000 COT - ENGR - Site - Assurance Release KMARKS Correction Required Entered by FRODRIGU -
06/26/2000 COT - ENGR - Site - Assurance Release KMARKS Correction Required Entered by FRODRIGU -
10/20/2000 COT - ENGR - Site - Assurance Release MFLICK Correction Required Entered by FRODRIGU -
11/09/2000 COT - ENGR - Site - Assurance Release LTHURSTO Correction Required Entered by FRODRIGU -
06/29/2000 COT - ENGR - Site - Assurance Release LTHURSTO Correction Required Entered by PKRAUSMA - SIGNED SEWER SERVICE AGREEMENTS REQUIRED
12/01/2000 COT - ENGR - Site - Assurance Release CPINTOR Correction Required Entered by FRODRIGU -
10/24/2000 COT - ENGR - Site - Assurance Release PGEHLEN APPR Entered by FRODRIGU -
01/03/2000 COT - ENGR - Site - Assurance Release MONEILL APPR Entered by JVOGELSB - APPROVED
01/07/2000 COT - ENGR - Site - Assurance Release DRUIZ APPR Entered by JVOGELSB - APPROVED
01/10/2000 COT - ENGR - Site - Assurance Release AQUINN APPR Entered by JVOGELSB - APPROVED
01/10/2000 COT - ENGR - Site - Assurance Release CRAIGEN APPR Entered by JVOGELSB - APPROVED
01/18/2000 COT - ENGR - Site - Assurance Release CPINTOR APPR Entered by JVOGELSB - APPROVED
12/18/1999 COT - ENGR - Site - Assurance Release JEGAN Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
01/07/2000 COT - ENGR - Site - Assurance Release SKING APPR Entered by JVOGELSB - APPROVED
03/03/2016 COT - ENGR - Site - Assurance Release DROBERTS Approved Entered by DROBERT5 -
05/14/2008 COT - ENGR - Site - Assurance Release DROBERTS Partial Approval Entered by DROBERT2 - MET WITH THE DEVELOPER ON SITE TO LOOK OVER WHAT HE IS ASKING FOR. HE WILL BE SUBMITTING FOR THE LOTS THAT HAVE BEEN COMPLETED AT THIS TIME. THE CURRENT STATUS OF THE LOTS ARE AS FOLLOWS. LOTS 1-6, 20, 24-26 ARE NOT BEING DEVELOPED AT THIS TIME. LOTS 17-19, AND 23 ARE BEING SET FOR FLOOR SLAB INSTALLATION. LOTS 21, 22, 27, & 28 ARE CURRENTLY BEING FRAMED AND STUCCOED. LOTS 7-16 HAVE BEEN COMPLETED FULLY EXCEPT THE SOUTHERN SIDEWALK OF LOT 16, THIS SIDEWALK WILL BE POURED NEXT WEEK. THE DEVELOPER HAS BEEN ADVISED THAT THE RETENTION/DETENTION BASIN WILL NEED TO BE COMPLETED FULLY BEFOR HE RECEIVES ANY LOTS PAST THE 75%, HE WILL WORK ON COMPLETING THIS ITEM A.S.A.P. AND WILL ADVISE WHEN THE WORK IS DONE. I WILL RECHECK THIS AREA IN 2 WEEKS TO SEE IF IT HAS BEEN COMPLETED.
05/09/2008 COT - ENGR - Site - Assurance Release DROBERTS Partial Approval Entered by DROBERT2 - LOOKED AT THE SITE CURRENTLY THE DEVELOPER IS COMPLETED 10 UNITS AND IS WORKING ON 4 OTHERS. THEY HAVE BEEN APPROVED FOR THE RELEASE OF 75% OF THE LOTS WHICH IS 21 FOR THIS SITE. NO ONE IS ON THIS SITE AT THIS TIME TO VERIFY WHAT IS BEING REQUESTED AT THIS TIME, I WILL TRY TO COME TO THIS SITE NEXT WEEK TO SEE WHAT THE DEVELOPER IS REQUESTING.
03/14/2008 COT - ENGR - Site - Assurance Release DROBERTS Partial Approval Entered by DROBERT2 - THIS SITE WAS RECHECKED FOR THE FINAL INSPECTION BUT NO CHANGES HAVE BEEN MADE TO THE COMMENTS FROM THE PREVIOUS INSPECTION DATED 2/22/08. THE ONLY THING THAT HAS CHANGED ON THIS SITE SINCE THE PREVIOUS INSPECTION IS THAT THE CONSTRUCTION OF LOT #16 HAS STARTED
02/22/2008 COT - ENGR - Site - Assurance Release DROBERTS Partial Approval Entered by DROBERT2 - THE SITE HAS BEEN CHECKED FOR THE INITIAL RELEASE OF THE SUBDIVISION AND HAS BEEN FOUND TO BE COMPLETE AT THIS TIME. A RE-INSPECTION OF THE SITE WILL BE REQUIRED PRIOR TO THE SITE RELEASES REACHING 75% OF THE PROJECT RELEASES.
01/10/2000 COT - ENGR - Site - Assurance Release KMARKS Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
01/04/2000 COT - ENGR - Site - Assurance Release AMODICA Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
01/07/2000 COT - ENGR - Site - Assurance Release LTHURSTO Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
01/07/2000 COT - ENGR - Site - Assurance Release FREYES Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
04/05/2000 COT - ENGR - Site - Assurance Release DRIVERA APPR Entered by FRODRIGU - WITH CONDITIONS
01/11/2000 COT - ENGR - Site - Assurance Release DRIVERA Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
06/04/2001 COT - ENGR - Site - Assurance Release MBERGHUI APPR Entered by FRODRIGU - CONDITIONAL APPROVAL
12/29/1999 COT - ENGR - Site - Assurance Release THARVISO Correction Required Entered by JVOGELSB - CORRECTION REQUIRED
06/30/2000 COT - ENGR - Site - Assurance Release Passed
08/27/2001 COT - ENGR - Site - Assurance Release Passed
08/27/2001 COT - ENGR - Site - Assurance Release Passed
08/27/2001 COT - ENGR - Site - Assurance Release Passed
12/29/1999 COT - ENGR - Site - Assurance Release STAFF APPR Entered by JVOGELSB - APPROVED