Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - ENGR - Site - Assurance Release
Plan Number - S19-039
Inspection Description - COT - ENGR - Site - Assurance Release
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/07/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - PARTIAL OK TO RELEASE THE FOLLOWING LOTS 185, 187, 192, 214. |
10/05/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by VVERA1 - OK TO RELEASE LOTS 215 |
09/30/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - PARTIAL ATH THIS TIME OK TOO RELEASE LOT 223 |
09/01/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - OK TO RELEASE LOTS 175,180,181,183,186,217,218,219,220 ,221,222. |
08/26/2022 | COT - ENGR - Site - Assurance Release | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. Lot 191 is OK for release. |
08/12/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL, OK TO RELEASE LOT #149 |
08/04/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - OK TO RELEASE LOT 188,189,190,198,207,212. |
07/08/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL OK TO RELEASE LOTS 193 AND 211 |
07/05/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - OK TO RELEASE LOTS 93,194,196,206,209,210,213,216. |
06/10/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by VVERA1 - IS PARTIAL OK FOR THE RELEASE IF LOTS 151 AND 153. |
05/06/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL AT THIS TIME, OK TO RELEASE ? LOTS 143, 146, 147 |
03/18/2022 | COT - ENGR - Site - Assurance Release | BBENEDON | Partial Approval | Entered by VVERA1 - Partially approved OK to release Lot 169. |
03/10/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Continued | Entered by RSALDAT1 - CN OK TO RELEASE LOTS 137,138,139,140,141,142,160 AND 173. |
03/08/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by VVERA1 - PARTIAL OK TO RELEASE LOTS 168, 170, 171, 172. |
01/07/2022 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by VVERA1 - IS PARTIAL, OK TO RELEASE LOT 158 |
01/03/2022 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by VVERA1 - OK TO RELEASE LOTS 93,94,95,159,160,161.162,163,164,165,AND 167. |
11/30/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by VVERA1 - OK TO RELEASE LOT 82 |
11/24/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - OK TO RELEASE LOT 81 |
10/06/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - OK TO RELEASE LOTS 11,35,AND 46 |
08/19/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - OK TO RELEASE LOTS 14,28,29,30,31,32,33,36,37,41,42,43,44,45 AND 47. |
07/16/2021 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - PARTIAL APPROVED, OK FOR THE RELEASE OF LOT 99 ONLY |
07/15/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - Release OKLots 27,72,75,76,77,78,79,80,96,97,98,100,101. |
06/30/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - OK TO RELEASE LOTS 25,26,73 AND 74 |
06/03/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by VLEON1 - OK TO RELEASE LOTS 71,102,103,AND 104. LOT 71 NEED TO COMPLETE THE LANDSCAPE.LOT 104 AND 102 LANDSCAPE IS NOT COMPLETED |
04/28/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by VLEON1 - Release OK? Lots 20,21,67,69,106. |
03/26/2021 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by VLEON1 - PARTIAL, OK TO RELEASE THE FOLLOWING LOTS 22, 23, 24,66,68,70,105,107 and 108. |
03/24/2021 | COT - ENGR - Site - Assurance Release | MHERNANDEZ | Partial Approval | Entered by RSALDAT1 - OK TO RELEASE LOTS 13,19,48,55,63,64,65. And 119 .WII NEED TO REINSPECTED AT A LATER DATE. |
02/18/2021 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - PARTIAL OK TO RELEASE THE FOLLOWING LOTS 18,53,54,56,57,58,59,60. |
12/28/2020 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - OK TO RELEASE LOT #166 |
12/17/2020 | COT - ENGR - Site - Assurance Release | DROBERTS | Partial Approval | Entered by RSALDAT1 - IS PARTIAL OK TO RELEASE LOTS 15,16,17,49,50,51,52,109,110,111,112,118,120,130 |
12/04/2020 | COT - ENGR - Site - Assurance Release | BBENEDON | Partial Approval | Entered by PAHUMAD1 - Partially approved. Lots 124 through 128 |
11/30/2020 | COT - ENGR - Site - Assurance Release | RLEDONNE | Partial Approval | Entered by PAHUMAD1 - Partial approval. OK for release of Lot 136. |
11/19/2020 | COT - ENGR - Site - Assurance Release | RLEDONNE | Partial Approval | Entered by PAHUMAD1 - (assurance - DSD ) partial approval. OK for lot releases for lots. 61,62,115,116,117,123,129,131,132,133,and 134. |
11/04/2020 | COT - ENGR - Site - Assurance Release | RLEDONNE | Partial Approval | Entered by PAHUMAD1 - Partial approval. OK for lot releases on lots 113,114,121,122,and 135 |
01/06/2023 | COT - ENGR - Site - Assurance Release | Partial Pass | OK FOR THE RELEASE OF Lot 226 | |
02/03/2023 | COT - ENGR - Site - Assurance Release | Partial Pass | LOT 178 RELEASE | |
02/13/2024 | COT - ENGR - Site - Assurance Release | Passed | Assurance RELEASE LOTS 9AND 10 | |
02/15/2024 | COT - ENGR - Site - Assurance Release | Passed | All remaining inspections for this site lot, specific sidewalks and driveways, and will be done during the inspection for the home itself | |
05/16/2023 | COT - ENGR - Site - Assurance Release | Partial Pass | Full & Final Release for Phase 1A & 1B requested. - All Lots and common areas Dave Roberts will give you full release I’m only going to give you a Partial | |
05/17/2023 | COT - ENGR - Site - Assurance Release | Partial Pass | Full & Final Release for Phase 1A & 1B requested. - All Lots and common areas Call Dave Roberts he will give you the full release | |
05/19/2023 | COT - ENGR - Site - Assurance Release | Not Ready | Full & Final Release for Phase 1A & 1B requested. - All Lots and common areas. I met with Jake from KB homes to discuss things that will probably be needed for the site prior to doing a full release of the Subdivision Provide this department, a copy of the Revised Landscape Plans and drawings for the site to be utilized for the Final Inspection. Once this inspection has been performed, we will then look at can we consider in Full release of all lots blocks and common areas for the Subdivision. |
|
11/08/2022 | COT - ENGR - Site - Assurance Release | Basin - Good | Partial lot release okay? Lot 176. | |
11/18/2022 | COT - ENGR - Site - Assurance Release | Basin - Good | OK for assurance release | |
12/01/2022 | COT - ENGR - Site - Assurance Release | Passed | THE SITE HAS BEEN INSPECTED FOR THE RELEASE OF THE FOLLOWING LOTS FROM THE ASSURANCES: LOTS #174, 176, 182, AND #184 | |
12/01/2022 | COT - ENGR - Site - Assurance Release | Passed | THE SITE HAS BEEN INSPECTED FOR THE RELEASE OF THE FOLLOWING LOTS FROM THE ASSURANCES: LOTS #224 AND #225. | |
12/05/2023 | COT - ENGR - Site - Assurance Release | Not Ready | AS PREVIOUSLY DISCUSSED THIS PAST THURSDAY 12/1/23 WITH JAKE WALLACE, KELLY LEE, AND JESSE TARAZON AND PRIOR MEETINGS IN THE PAST, THE COMMON AREAS ARE NOT READY AND NEED TO BE REINSPECTED PRIOR TO A FINAL RELEASE. THE COMMON AREAS THAT CAN BE LOOKED AT CURRENTLY ARE IN BELLA TIERRA PHASE II AND WILL BE CONSIDERED. THIS INSPECTION WILL BE RESCHEDULED WITH JAKE FROM KB HOMES AN MYSELF FOR 12/7 TO VERIFY THAT ALL WORK HAS BEEN DONE PER THE APPROVED PLANS. | |
12/06/2022 | COT - ENGR - Site - Assurance Release | Partial Pass | OK to release 1-A 1-B 1-227. LOTS 179 & 227, & 177 | |
12/26/2023 | COT - ENGR - Site - Assurance Release | Passed |