Inspection Status: Approved
Inspection History: ASSURANCE - DSD
| Date |
Description |
Inspector |
Results |
Comments |
| 06/29/2021 |
ASSURANCE - DSD |
|
Approved |
|
| 01/19/2021 |
ASSURANCE - DSD |
|
Partial Approval |
PARTIAL FOR 8211 E LEE ST - PARTIAL AT THIS TIME, OK TO RELEASETHE FOLLOWING LOTS 1,3,7,10,11. |
| 01/07/2021 |
ASSURANCE - DSD |
|
Not ready for Inspection |
IS NOT READY AT THIS TIME, COMPLETE ALL THE WORK FOR THE DEVELOPMENT PACKAGE PRIOR TO CALLING IN FOR THE FULL RELEASE OF THIS SITE. LOTS ON THIS SITE CAN BE RELEASED, BUT NOT ALL THE LOTS AND COMMON AREAS AT THIS TIME. HOLD LOTS 2 AND 12 TILL ADDITIONAL WORK IS COMPLETED. |
| 06/04/2020 |
ASSURANCE - DSD |
|
Partial Approval |
ok to release lots 4,5,6,8,9 |
| 03/24/2020 |
ASSURANCE - DSD |
|
Partial Approval |
INITIAL RELEASE OF THE SITE CAN BE DONE ONCE WE HAVE RECEIVED THE ACCEPTANCE LETTER FOR MAINTENANCE FROM TUCSON WATER DEPARTMENT, AND THE AUTHORIZATION OF DISCHARGE LETTER FROM PIMA COUNTY WASTEWATER FOR THIS SITE. IF THERE ARE ANY QUESTIONS PLEASE FEEL FREE TO CONTACT DAVID ROBERTS AT (520) 349-7643, OR BY EMAIL AT David.Roberts@tucsonaz.gov. |