Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case: S18-004

Parcel: 99999999A

Inspection Status: Passed

Inspection History: TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance)

Plan Number - S18-004

Inspection Description - TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance)

Inspection Status - Passed

Date Description Inspector Results Comments
04/10/2020 TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) RLEIGH Approved Entered by AHINES2 -
04/10/2020 TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) RLEIGH Approved Entered by AHINES2 -
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) Partial Pass
05/21/2024 TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) Passed