Inspection Status: Approved
Inspection History: ASSURANCE - DSD
| Date |
Description |
Inspector |
Results |
Comments |
| 05/29/2020 |
ASSURANCE - DSD |
|
Approved |
APPROVED FOR RELEASE OF ALL LOTS AND COMMON AREAS |
| 05/12/2020 |
ASSURANCE - DSD |
|
Approved |
APPROVED AT THIS TIME PENDING ALL OTHER INSPECTIONS |
| 03/11/2020 |
ASSURANCE - DSD |
|
Partial Approval |
THE FOLLOWING ITEMS WERE NOTED DURING THE WALK THROUGH 1) STAKING OF THE TREES ARE NOT PER THE APPROVED PLANS, STAKE AS NEEDED AND REMOVE ALL NURSERY STAKES. 2) THE PLAN CALLS FOR 6 SAGUARO CACTUS, 6 FEET IN HEIGHT, THESE HAVE NOT BEEN INSTALLED AT THIS TIME. 3) GENERAL SITE CLEAN UP AS NEED IN AND AROUND THE SITE, REMOVE ALL CONSTRUCTION TRASH AND DEBRIS FROM ALL COMMON AREAS. 4) COMPLETE ALL OF THE INSPECTIONS FOR THIS PERMIT S17-065, DEVELOPMENT PACKAGE DP17-0207, PROVIDE ALL CLOSE OUT DOCUMENTATION AS NEEDED. |
| 02/14/2020 |
ASSURANCE - DSD |
|
Not ready for Inspection |
AT THIS TIME FOR ANY FULL RELEASE OF ANY LOTS, BLOCKS, AND COMMON AREAS. I DROVE THE SITE WITH JOHN VAN WINKLE AND DISCUSSED THE WORK THAT HAS HAPPENED TO THIS DATE. THE COMMON AREAS HAVE NOT BEEN COMPLETED AS SHOWN ON THE APPROVED PLANS SO NOT COMPLIANT ENOUGH FOR THEM TO BE RELEASED. JOHN WILL DISCUSS THE CURRENT SITE CONDITIONS WITH THE TITLE AGENT, AND HELP DETERMINE WHEN ADDITIONAL INSPECTIONS WILL BE REQUIRED. |
| 11/25/2019 |
ASSURANCE - DSD |
|
Partial Approval |
ok to release lots 1,4,5,6,7,9,12 |
| 09/12/2019 |
ASSURANCE - DSD |
|
Partial Approval |
ok to release lot 3 |
| 05/31/2019 |
ASSURANCE - DSD |
|
Partial Approval |
OK FOR ADDITIONAL RELEASES FOR THIS SITE, FINAL NOT TO BE GIVEN AT THIS TIME. COMPLETION BOND AND CLOSE OUT DOCUMENTS ARE REQUIRED BEFORE A FULL RELEASE OF THE ASSURANCES. |