Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case: S17-005

Parcel: 30509004C

Inspection Status: Approved

Inspection History: ASSURANCE - DSD

Plan Number - S17-005

Inspection Description - ASSURANCE - DSD

Inspection Status - Approved

Date Description Inspector Results Comments
07/06/2020 ASSURANCE - DSD Approved OK TO RELEASE ALL LOTS, BLOCKS, AND COMMON AREAS.
06/15/2020 ASSURANCE - DSD Partial Approval PARTIAL AT THIS TIME, 6 LOTS REMAIN WITHOUT SIDEWALKS AND DRIVEWAYS, 2 OF THE 6 LOTS HAVE NO CONSTRUCTION ON THEM AT THIS TIME. IF A COMPLETION BOND IS IN PLACE AT THIS TIME FOR THE SIDEWALK AND DRIVEWAYS THIS MAY BE CONSIDERED COMPLETE.
06/09/2020 ASSURANCE - DSD Partial Approval SWPPP termination letter uploaded
05/01/2020 ASSURANCE - DSD Partial Approval IS PARTIAL AT THIS TIME, OK FOR THE RELEASE OF LOTS 3 & 8. THERE HAS BEEN DAMAGED SIDEWALK NOTED DURING THE PAST INSPECTIONS THAT NEED TO BE REMOVED AND REPLACED PRIOR TO THE FINAL ACCEPTANCE OF THIS SUBDIVISION AND THE DEVELOPMENT PACKAGE/TENTATIVE PLAT. THE DEVELOPER NEEDS TO WALK THIS SITE AND CHECK FOR ALL DAMAGES THAT WILL NEED TO BE REPAIRED PRIOR TO THE FINAL APPROVAL.
04/23/2020 ASSURANCE - DSD Partial Approval Once the Clerk records the substitute assurance agreement removing lot specific sidewalks for S17-005, we will process a full and final release of assurances, unless there are results listing incomplete infrastructure.
04/23/2020 ASSURANCE - DSD Approved Construct all lot specific sidewalks or wait for recorded substitute trust assurance agreement.
03/12/2020 ASSURANCE - DSD Approved OK for lot releases 4,11,and20.
02/13/2020 ASSURANCE - DSD Partial Approval ok to release lots 13,15,33. Trust agent informed that release is beyond 75% and that no further lots will be released until all work is complete or a substitute agreement is recieved
11/25/2019 ASSURANCE - DSD Partial Approval ok to release lot 18.
08/14/2019 ASSURANCE - DSD Not ready for Inspection RELEASES CAN BE SOUGHT FOR THE COMMON AREAS, OR PLACE A COMPLETION BOND FOR ALL REMAINING ASSURABLE ITEMS. THE LOTS BELOW ARE COMPLETED IN THE FOLLOWING MANNER:

1) VACANT NOT CONSTRUCTED UPON, LOTS: 1-4, 6-8, 10-13, 15-18, 20-21, 32-33, 35-36.

2) UNDER CONSTRUCTION ON LOTS: 5, 14, 23, 26, 29, 37-38, 42, 47, 49.

3) COMPLETED ON LOTS: 9, 19, 22, 24-24272830-31, 34, 39-41, 43-46, 48, 50-55
07/19/2019 ASSURANCE - DSD Partial Approval ok to release lots 5,9,21,23,29,38,42. Lot release total now at 74.5%
04/18/2019 ASSURANCE - DSD Partial Approval
03/22/2019 ASSURANCE - DSD Partial Approval OK TO RELEASE LOTS 14, 30, 31, 34, 36, 37, 45
02/15/2019 ASSURANCE - DSD Partial Approval OK FOR INITIAL RELEASE AND OK TO RELEASE LOTS 25, 26, 40, 41