Inspection Status: Passed
Inspection History: TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance)
| Date |
Description |
Inspector |
Results |
Comments |
| 02/22/2018 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
RLEIGH |
Approved |
Entered by RLEIGH1 - |
| 03/17/2015 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - I RECIEVED THE LETTERS FROM RICHARD LEIGH SENT TO ME BY SEAN RICH FOR THE FOLLOWING APPROVALS: MOUNTAIN VAIL ESTATES PART "C" AND "F" STATING THAT ALL WORK FOR THE PIA IS COMPLETE AS OF JULY 9, 2014, THE DATE ON THE LETTER. |
| 02/22/2018 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
RLEIGH |
Approved |
Entered by RLEIGH1 - |
| 03/17/2015 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - PARTIAL APPROVAL FOR PART "C" LOTS 184 - 215 AND PART "F" LOTS 323 - 338, & LOTS 346 - 384 |