Inspection History Details
Inspection Status: Approved
Inspection History: ASSURANCE - DSD
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/23/2020 | ASSURANCE - DSD | Approved | OK TO RELEASE ALL LOTS, BLOCKS, AND COMMON AREAS FOR THIS SITE | |
| 06/25/2020 | ASSURANCE - DSD | Approved | 3PLT agreement may be closed. Remaining sidewalks and driveway aprons are held in a substitute assurance agreeement letter of credit | |
| 06/18/2020 | ASSURANCE - DSD | Approved | LOTS 1-3, AND LOT 43 SIDEWALKS AND DRIVEWAYS HAVE NOT BEEN POURED AT THIS TIME. THE FORMS HAVE BEEN PLACED AND CHECKED ON LOTS 1 AND 2, THE CROSS SLOPE VARIES IN THESE AREAS FROM 1% TO 1.7% | |
| 03/11/2020 | ASSURANCE - DSD | Approved | THE DEVELOPMENT PACKAGE FOR THIS SITE WILL NEED TO BE COMPLETED AND ALL OUTSTANDING INSPECTIONS APPROVED AND FINAL THE PERMIT | |
| 02/27/2020 | ASSURANCE - DSD | Not ready for Inspection | This site is not ready at this time for a foreclosure will discuss the site with John Van Winkle tomorrow morning to 28 2020 about it for closure by the middle of March currently one house under construction three houses still needs to be constructed on through a lot still left to be constructed on. | |
| 01/29/2020 | ASSURANCE - DSD | Continued | There are four remaining undeveloped lots, with no sidewalk. There’s one section of sidewalk under construction. There is erosion causing dirt on sidewalk In one location. There’s a dumpster blocking the sidewalk. There are material stock piles on site and some areas still requiring stabilization. Some stormwater controls are still in place. | |
| 11/25/2019 | ASSURANCE - DSD | Partial Approval | ok to release lots 4,10,37. applicant has submitted at substitute agreement to construct letter of credit that is currently in review at the clerks office | |
| 11/22/2019 | ASSURANCE - DSD | Partial Approval | ok to release lots 4,10,37. Substitute agreement, letter of credit is as attorneys office for review and tranfer to Clerks office | |
| 10/22/2019 | ASSURANCE - DSD | Partial Approval | ok to release lots 5 and 7. Customer is submitting a susbtitute agreement, letter of credit, for remaining assurable items. | |
| 07/10/2019 | ASSURANCE - DSD | Partial Approval | Lot 6 and 36. | |
| 02/11/2019 | ASSURANCE - DSD | Partial Approval | I PUT TOGETHER AN UPDATE OF THE SITE FOR JOHN VAN WINKLE SO THAT HE CAN SEE WHAT LOTS HAVE BEEN COMPLETED, CONSTRUCTED, AND STILL UNTOUCHED. | |
| 02/08/2019 | ASSURANCE - DSD | Partial Approval | LOOK AT THIS SITE AGAIN AND FOLLOWING CONDITIONS WILL NEED TO BE ADDRESSED PRIOR TO THE FULL RELEASE OF THE COMMON AREAS. 1) THERE IS STILL STANDING WATER NOTED IN THE COMMON AREA "C-2". THE ENGINEER OF RECORD WILL NEED TO PROVIDE TO THIS DEPARTMENT A RESOLUTION FOR THE STANDING WATER THAT EXCEEDS THE 24 HOUR LIMIT PER CODE. 2) PROVIDE THIS DEPARTMENT WITH A MONITORING REPORT FROM THE LANDSCAPE ARCHITECH NOTING ALL THE WORK THAT HAS BEEN DONE ON THIS SITE. IF THERE ARE ANY CHANGES OR MODIFICATIONS DONE TO THESE PLANS THEY WILL HAVE TO BE REVISED PRIOR TO THE FULL CLOSE OUT FOR THIS PROJECT. |
|
| 02/06/2019 | ASSURANCE - DSD | Partial Approval | LOOKED OVER THE SITE, AREAS LOOK CLOSE TO BEING READY. STANDING WATER NOTED IN THE COMMON AREA "C-2" FROM THE PREVIOUS RAINS. THIS WILL BE CHECKED ONE THE RAINS HAVE STOPPED FOR MORE T5HAN 24 HOURS. THERE HAS ALSO BEEN NOTED SEDIMENT IN THE DRAINAGEWAY BETWEEN LOTS 8 AND 9, AND ALSO ON THE SOUTH AND EAST SIDES OF LOT #10 IN THE DRAINAGE WAY TO THE BASIN. THESE AREAS WILL NEED TO BE CLEANED SO THAT THEY DRAIN CORRECTLY PRIOR TO THE FULL RELEASE OF THESE COMMON AREAS. |
|
| 01/15/2019 | ASSURANCE - DSD | Partial Approval | OK TO RELEASE THE FOLLOWING LOTS AT THIS TIME 8, 9, 31-35 | |
| 12/06/2018 | ASSURANCE - DSD | Partial Approval | Common areas ok for partial assurance release. | |
| 10/18/2018 | ASSURANCE - DSD | Continued | LOOKED OVER THE SITE TO SEE IF THE COMMON AREA BASINS HAVE BEEN COMPLETED AT THIS TIME. CURRENTLY IT APPEARS THAT THE SITE HAS NOT BEEN COMPLETED PER THE APPROVED PLANS. I WILL BE ASKING THE DEVELOPER TO PUT TOGETHER SOME OF THE PERSONNEL TO MEET ON SITE NEXT WEEK AND LOOK AT THE LANDSCAPING AND BASIN ITEMS. CURRENTLY THERE ARE SOME MISSING PLANTS AND A DETENTION/RETENTION BASIN THAT APPEARS NOT TO HAVE BEEN CONSTRUCTED. |
|
| 04/04/2018 | ASSURANCE - DSD | Denied | Common Areas may not be released until early October 2018 due to concerns with drainage and sediment in conjuction with monsoon season. | |
| 10/12/2017 | ASSURANCE - DSD | Partial Approval | OK FOR THER INITIAL RELEASE OF THE LOTS AT THIS TIME. FINAL NOT TO BE GIVEN TILL ALL WORK IS COMPLETED AS PER THE APPROVED PLANS, AND ALL INSPECTIONS ARE APPROVED. |