Case: S02-017

Parcel: 140292140


Addresses:

6300 S ALVERNON WY


Inspection Status: Passed

Inspection History: TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance)

Plan Number - S02-017

Inspection Description - TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance)

Inspection Status - Passed

Date Description Inspector Results Comments
01/11/2008 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) DLEE Approved Entered by SMONTIE1 - PLAN NO. : I-2002-043
12/21/2007 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) DLEE Approved Entered by SMONTIE1 - PLAN NO. : I-2003-21
12/05/2007 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) DLEE Denied Entered by SMONTIE1 - Plan No. : I-2002-043 This office inspected the subject project on December 5, 2007 and found the following items in need of attention. Please consider this letter the punch list of items to be addressed/ rectified prior to the acceptance of improvements in the public rights-of-way by the City of Tucson for maintenance and operation. Future inspections will require a Letter of Certification that all punch list items have been resolved by the Engineer of Record. In addition to the following items, Traffic Engineering may have additional punch list items pertaining to traffic signage and striping. 1. Please insure that the Right-of-way Excavation Permit is current prior working on any punch list items. If the permit is expired, a new permit for the P.I.A is required prior to any remedial work or re-inspection of the subject project. 2. Landings for the curb access ramps located at the northeast and southwest corner of Hemisphere Place and Sun View and the northwest corner of Sunrise Valley Drive and Sun View Way exceed the maximum allowable cross slope. 3. Survey monuments that were replaced have not been punched or stamped. 4. Steel scupper on Transcon Way between Lots 110 and 111 is to be painted.
12/05/2007 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) DLEE Denied Entered by SMONTIE1 - PLAN NO. : I-2003-021 This office inspected the subject project on December 5, 2007 and found the following items in need of attention. Please consider this letter the punch list of items to be addressed/ rectified prior to the acceptance of improvements in the public rights-of-way by the City of Tucson for maintenance and operation. Future inspections will require a Letter of Certification that all punch list items have been resolved by the Engineer of Record. In addition to the following items, Traffic Engineering may have additional punch list items pertaining to traffic signage and striping. 1. Please insure that the Right-of-way Excavation Permit is current prior working on any punch list items. If the permit is expired, a new permit for the P.I.A is required prior to any remedial work or re-inspection of the subject project. 2. Survey monuments that were replaced have not been punched nor stamped. 3. There is a failing patch in front of the address of 6130 E. Earp Wash. 4. There is failing patch/ pavement in front of 3878 E. Eventide Street.
11/15/2007 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) TSTOCKET Approved Entered by SMONTIE1 - PLAN NO. : I-2002-043
11/30/2007 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) TSTOCKET Approved Entered by SMONTIE1 - PLAN NO. : I-2003-021
01/22/2008 TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) TSTOCKET Approved Entered by THAUSER1 - I-2004-026