Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP22-0284
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/05/2024 | ENGR Engineering Final | Not Ready | Information only on this trip | |
07/24/2024 | ENGR Engineering Final | Partial Pass | A TCO4 can be issued now and a full CO once items in the pictures have been corrected. 1) pic shows a supposed concrete weir and broken tree stake. 2) shows a cracked concrete panel 3) cone covering a valve 4) tree limbs over a pedestrian pathway. 5) dead tree 6) please continue all the way to the end |
|
08/09/2024 | ENGR Engineering Final | Not Ready | Not ready at this time. The basins have not been constructed per the approved plan on the northern side of his property and on the south west corner of the property around the trash enclosure. Provide the city of Tucson with your notice of termination from the Arizona Department of environmental quality prior to requesting another inspection for the stormwater final. Spots of non-compliancy was noted throughout the ADA Parking Spaces and access aisles, this will be rechecked on Monday Next week. |
|
08/21/2024 | ENGR Engineering Final | Canceled | ||
08/28/2024 | ENGR Engineering Final | Partial Pass | Everything has been completed other than the couple of ADA parking spaces, we are still observing the TCO4. Once parking spaces are compliant we can sign off on the full CO | |
09/05/2024 | ENGR Engineering Final | Passed |