Inspection Status: Partial Pass
Inspection History: COT - ENGR - Stormwater
| Date |
Description |
Inspector |
Results |
Comments |
| 04/14/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
Stormwater catch basins |
| 04/21/2023 |
COT - ENGR - Stormwater |
|
Complete (Recurring) |
Frank Lopez. Plans under review. Stormwater is the only inspection attached to the permit at this time. |
| 05/25/2023 |
COT - ENGR - Stormwater |
|
Complete (Recurring) |
no issues or concerns at this time |
| 05/31/2023 |
COT - ENGR - Stormwater |
|
Complete (Recurring) |
Final grading in progress. Curb installations. |
| 06/15/2023 |
COT - ENGR - Stormwater |
|
Complete (Recurring) |
Landscaping material piles on site. No controls in place. Landscaping work in progress |
| 06/20/2023 |
COT - ENGR - Stormwater |
|
Not Ready |
COMPLETE THIS SITE AS SHOWN ON THE APPROVED PLANS |
| 06/22/2023 |
COT - ENGR - Stormwater |
|
Passed |
|
| 07/05/2023 |
COT - ENGR - Stormwater |
|
Partial Pass |
|
| 07/13/2023 |
COT - ENGR - Stormwater |
|
Not Ready |
Complete all work as previously discussed |
| 08/08/2023 |
COT - ENGR - Stormwater |
|
Passed |
|