Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/13/2026 | ENGR - Drainage Structures | Partial Pass | Okay to begin backfilling ADS storage chambers, leaving east and west ends open as needed for nyloplast drain basins and HDPE drain pipe. Materials, elevations of chambers and compaction of pad correct. | |
| 08/21/2026 | ENGR - Drainage Structures | Partial Pass | -Connections made to east side of Storage chambers and 18" HDPE Sections. Slope, bedding alignment correct. Okay to place stone and filter fabric at east side but take pictures of joints with Geotextile filter fabric at connections and crushed stone placement and depths. -24" HDPE between CB 1 and storage chambers bedded and sloped correct okay to backfill PIpe and Nyloplast Drain Basin with correct crushed stone and bedding. -18" HDPE Pipe on east side at entrance between CB 2 and 3 correct okay to backfill pipe between Drain Basins. -Schedule inspections for West side of storage chamber, drain basin and connections and the rest of the NyloPlast drain basins as they are ready placed on crushed stone bedding. |
|
| 09/09/2026 | ENGR - Drainage Structures | Partial Pass | Okay to pour invert of CB#3. | |
| 09/23/2026 | ENGR - Drainage Structures | Partial Pass | Okay to pour walls for CB 1a, & 3 |