Inspection Status: Not Ready
Inspection History: Final inspection to ensure all landscape and water harvesting SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 11/09/2023 |
Final inspection to ensure all landscape and water harvesting SITE |
|
Not Ready |
The contractor is working on installing the last Of the landscaping and installing the DG as needed throughout the site. I have brought it to their attention that the water harvesting areas are not deep enough and will need to be increased in depth. Per the approved plans there is to be 6-9 inches of free board space above the decomposed granite below the lowest inlet structure within the area. This Inspection will be rescheduled for Monday of next week by the prime Contractor. |
| 11/13/2023 |
Final inspection to ensure all landscape and water harvesting SITE |
|
Passed |
|