Inspection History Details
Inspection Status: Partial Pass
Inspection History: Final inspection to ensure all landscape and water harvesting SITE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2023 | Final inspection to ensure all landscape and water harvesting SITE | Partial Pass | Will review River rock locations and disturbed storm water drain areas for possible hydro seeding requirements. Will review NE corner drain block height . Handicap sign located at North end of vacuum station area will need to be raised to 7’ bottom of sign (height is currently at 5’-6”) at bottom of sign. Various site signs at entry and exit points are currently being installed and to be completed the 16th of this week. Inspections will be recalled on Thursday November 1 |
|
| 11/16/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed |