Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/10/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - MET RENAE ON SITE TO DISCUSS WHAT THEY WILL BE DOING WITH THE 18 IN CMP PIPE THAT HAS BEEN FOUND ON THE WEST SIDE PROPERTY LINE. HE IS WORKING WITH HIS ARCHITECT TO COME UP WITH A SOLUTION FOR EXTENDING THE CMP THROUGH HIS PROERTY SO THAT THE NATURAL FLOW PATTERNS CAN BE MAITAINED.
I DISCUSSED THE PROPOSAL WITH STEPHEN BLOOD THIS MORNING AND IT APPEARS THAT THIS WILL BE A VIABLE SOLUTION AS LONG AS IT IS VERIFIED, STAMPED, AND SIGNED OFF BY THE ARCHITECT OF ENGINEER OF RECORD IN THE FINAL DOCUMENTATION. |
| 05/11/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by DROBERT5 - LOOKED OVER THE SITE TO SEE THAT THE CONTRACTOR HAS DUG A TRENCH THROUGH THE PROJECT INTERIOR FOR THE PLACEMENT OF AN 18 INCH CMP. THEY WILL BE CONNECTING TO THE END OF THE EXISTING CMP (AT THE WEST SIDE OF THE PROPERTY) THAT RUNS UNDERNEATH THE CAMINO ARRIBA ROADWAY AND RUN A NEW SECTION OF PIPE NORTH ALONG THE WESTERN BOUNDARY, AND TURN THE PIPE EAST SOUTH OF THE NORTHERN PROPERTY LINE TO ALLOW THE WATER TO DRAIN BACK INTO THE ORIGINAL FLOWLINE. THIS WORK WILL BE INSPECTED BY THE ARCHITECT OR AN ENGINEER OF RECORD PRIOR TO ALLOWING THE PLACEMENT OF THE BACKFILL MATERIAL. |
| 05/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 05/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 05/25/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |