Permit: DP22-0081

Parcel: 141366860

Inspection Status: Not Ready

Inspection History: PDSD Site/Engineering Division - NPPO

Permit Number - DP22-0081

Inspection Description - PDSD Site/Engineering Division - NPPO

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/26/2022 PDSD Site/Engineering Division - NPPO Not Ready
02/06/2023 PDSD Site/Engineering Division - NPPO Complete (Recurring) Need to get a hold of the contractor because I do not notice a nursery in the area
06/23/2023 PDSD Site/Engineering Division - NPPO Complete (Recurring) Continue watering the plants at the nursery
09/08/2023 PDSD Site/Engineering Division - NPPO Not Ready call KENG superintendent, Kyle Shepard, but there’s no answer I can’t find the nursery for the NPPO. Contractors going to need to reschedule.
09/29/2023 PDSD Site/Engineering Division - NPPO Not Ready Complete this site as shown on the Approved plans. This Inspection will not be completed till the Landscape Plans have been Utilized for this Inspection
09/29/2023 PDSD Site/Engineering Division - NPPO Not Ready Complete this site as shown on the Approved plans. This Inspection will not be completed till the Landscape Plans have been Utilized for this Inspection
10/04/2023 PDSD Site/Engineering Division - NPPO Re-inspection required 1) NPPO is not in compliance and needs serious attention. Several plants are or seam to be deceased/dead.
10/27/2023 PDSD Site/Engineering Division - NPPO Not Ready West parcel (6) there are only curbs and no sidewalks the pads on Paseo Alga to Paseo Obelo are completed and have utilities, The pads on Paseo Monte De Oro and Paseo Alga to Via Bombachas are completed with utilities.

On Paseo Baranda lots 67 thru 75 are frame completed and lot 71 and 72 are Lath completed.

Lots 65 and 66 are in framing stage.

Lots 62,63,64 are at slab poured stage.
10/27/2023 PDSD Site/Engineering Division - NPPO Not Ready Provide the landscape plans that will be utilized for this site and all the other sites so that this work can be inspected and approved