Inspection Status: Not Ready
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
SITE - Stormwater Follow-up
|
|
Not Ready |
|
| 03/16/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
No concerns at this time everything looks good |
| 03/24/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Ok to backfilling the 24 storm drain on the east side of the building. |
| 03/28/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Installed 12 inch HDP pipe on the northside of the building good backfield. |
| 04/03/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Contractor formed up for the floors on 2-12” inch pipes and 3 -24 inch pipe |
| 04/05/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Forming up fresh for catch basins two on the north side and one on the east side and one on the south east side good rapport |
| 05/01/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
No concerns at this time |
| 06/27/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
no concerns at is time |
| 11/15/2023 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
The basins and water harvesting areas are not completed yet |
| 11/16/2023 |
SITE - Stormwater Follow-up
|
|
Re-inspection required |
No concerns at this time. Still implementing storm water systems. |
| 12/15/2023 |
SITE - Stormwater Follow-up
|
|
Passed |
|