Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP22-0072
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | Not Ready | ||
10/27/2022 | ENGR Engineering Final | Not Ready | ||
11/02/2023 | ENGR Engineering Final | Partial Pass | Contractor is looking for a TCO and I cannot give it to him at this time because of the roof drainage onto the concrete area. Dave Roberts is scheduled to come out and take a look at it and talk to the superintendent. | |
11/09/2023 | ENGR Engineering Final | Partial Pass | OK FOR A LEVEL 2 TCO FOR STOCKING AND TRAINING | |
12/13/2023 | ENGR Engineering Final | Partial Pass | Contractor needs to finish all the landscaping around the whole area and the parking lot trees need to be planted. DG needs to be placed. HYDROSEEDING needs to be placed in the grade on the west side needs to be re-cut. | |
12/15/2023 | ENGR Engineering Final | Passed | ||
12/15/2023 | ENGR Engineering Final | Passed | ||
12/15/2023 | ENGR Engineering Final | Passed | Ok for a level 4TCO |