Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP22-0066
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
03/30/2023 | ENGR Grading Final | Partial Pass | Trash enclosure footing. Terry. | |
04/10/2023 | ENGR Grading Final | Complete (Recurring) | Inspection for trash enclosure contractor needs install number four rebar for the bond beams on top on both trash and closures the trash enclosure on the north side has no knockout for the grouting to come out | |
07/12/2023 | ENGR Grading Final | Passed | ||
08/08/2023 | ENGR Grading Final | Passed | ||
08/08/2023 | ENGR Grading Final | Passed | ||
08/08/2023 | ENGR Grading Final | Passed | ||
12/01/2022 | ENGR Grading Final | Complete (Recurring) | The crews have worked on installing the vertical curb for the roadway on the north side of this site. They are planning on playing the asphalt for the roadway in the next two weeks once they have completed the compaction of the ABC. |