Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP22-0033

Parcel: 137055850


Addresses:

4400 S LANDING WY


Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Permit Number - DP22-0033

Inspection Description - ENGR Grading Final

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
01/18/2024 ENGR Grading Final Partial Pass Double trash enclosure located on SW end of site #4 horizontal rebar for apron and mat is completed per COT requirements and ready for concrete pour.
03/14/2024 ENGR Grading Final Partial Pass Verified (27) parking structure column footers at a 6’ depth and 2’ diameter located at North, NW, and NE sections of parking lot areas.
05/14/2024 ENGR Grading Final Not Applicable
05/14/2024 ENGR Grading Final Passed
05/14/2024 ENGR Grading Final Passed
05/24/2023 ENGR Grading Final Complete (Recurring) Setting number six steel for the footers for trash enclosures one on the north Eastside and the other one is on the south east side
06/07/2023 ENGR Grading Final Complete (Recurring) Grading for trash enclosures good
06/09/2023 ENGR Grading Final Partial Pass The inspection today it was utilized to look at the trash and closures on the north east and south east corners of the site. The contractor has constructed the lower 4 feet and will be grabbing that this coming week and then will continue with the upper portions of the trash and enclosure.
06/12/2023 ENGR Grading Final Complete (Recurring) Contractor is good to grout the first 4 feet of trash enclosures the one on the southwest side and the one on the northwest side trash enclosures.
06/14/2023 ENGR Grading Final Complete (Recurring) Contractor is grouting the last 4 foot of the trash and closure the one on the north west corner and the one on the south west corner
06/25/2024 ENGR Grading Final Partial Pass Water flow from parking lot and building have washed out the drainage areas in several spots impacting basin, this was after one storm.
1) left side of building at lot drain to basin.
2) Both left side roof drains
3) All rear roof drains.
07/09/2024 ENGR Grading Final Passed Letter from engineer has been received and this inspection can be considered as passed.
07/11/2024 ENGR Grading Final Passed July 11th, 2024. Engineers letter has been received
07/13/2023 ENGR Grading Final Not Ready Reschedule for tomorrow for rebar and grading
07/14/2023 ENGR Grading Final Partial Pass ok to pour the trash enclosure located at the southwest corner of the site north of the PCL Construction job trailer for the Water Department site
08/21/2023 ENGR Grading Final Partial Pass Good to pour the floor for trash enclosure ONTHE south east side of the building.
08/25/2023 ENGR Grading Final Complete (Recurring) SW trash enclosure grout complete and ready to be capped.

The North end of SW courtyard trench and 12” pipe are ready for backfill.
08/29/2023 ENGR Grading Final Complete (Recurring) South East center of courtyard (2) 20’ trench sections completed with shading and 12” pipe ready for backfill.
08/31/2023 ENGR Grading Final Not Ready
09/18/2023 ENGR Grading Final Partial Pass Pole foundations, for the carports are good to pour
11/09/2022 ENGR Grading Final Complete (Recurring) 9152 stormwater installation of control installed 24 inch DP’s
11/09/2022 ENGR Grading Final Complete (Recurring) 9152 stormwater insulation of control 24 inch DP
12/07/2023 ENGR Grading Final Partial Pass all rebar is present for floor mat 12” oc and dobies are in place, and has been inspected by 3rd party Western Technologies and is ready for concrete.