Inspection Status: Not Ready
Inspection History: COT - ENGR - Stormwater
Permit Number - DP21-0299
Inspection Description - COT - ENGR - Stormwater
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2023 | COT - ENGR - Stormwater | Not Ready | The contractor is still working on this project is not ready for this inspection to be either partially approved for fully approved. They will be working on raising the manhole covers to finish pavement grades. They will be working on installing the handicap access signs for the parking spaces, they will be working on General cleanup of the site and removal of us excess material before this inspection is rescheduled for a final CofOor rescheduled for a temporary Cof0 | |
| 03/22/2023 | COT - ENGR - Stormwater | Passed |