Date Description Inspector Results Comments
10/26/2022 PDSD Site/Engineering Division - NPPO Not Ready
06/21/2023 PDSD Site/Engineering Division - NPPO Not Ready Randy at331-238-2253. Project appears to be new building at existing storage facility. Grading in progress. Work within the right of way in progress. No attachments found. contact not answering phone. Please schedule preconstruction inspection and all other required inspections for this permit.
07/10/2023 PDSD Site/Engineering Division - NPPO Partial Pass Contractor needs to finish the landscaping and some of the grading they have for landscaping and paint in the handicap parking area and signs need to be installed
07/12/2023 PDSD Site/Engineering Division - NPPO Not Ready Reschedule
07/25/2023 PDSD Site/Engineering Division - NPPO Not Ready Contractor needs to install riprap from the gutter of the roof drain to the valley gutter on the south end of the building. Needs railing on the back door of the building. Needs tree staking on the north end of the building.
08/09/2023 PDSD Site/Engineering Division - NPPO Partial Pass Contractors pouring sidewalk on the south end of the building. There is no NPPO on this project. Contractor also installed sidewalk scuppers along the south end of the building and adding a new ramp on the north west side of the main building.
08/11/2023 PDSD Site/Engineering Division - NPPO Passed