Inspection Status: Not Ready
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
|
| 01/12/2023 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
There is no contractor on site I spoke to the engineer of record they are going to reschedule the pre-con |
| 01/13/2023 |
PDSD Engineering Division Pre-Construction SITE |
|
Passed |
Pre-con meeting was held on site with a contractor and subcontractor project is ready to go at this time for construction. The posting of the site for the switch will be done sometime early next week and a reinspection will be done at that time. |