Inspection Status: Partial Pass
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 06/18/2024 |
PDSD Engineering Division Pre-Construction SITE |
|
Partial Pass |
Steve Collins had led them to believe that they were doing things correctly, that has been remedied. Possibility of a plan change coming for several items. Our Tucson requirements for a trash enclosure are on their plans so they have several things to remedy. Canopy is new and on a separate permit. |
| 07/26/2024 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
TI plans do not match DP. Pedestrian circulation incorrect. Refuse enclosure incorrect. Revise appropriate plans, resubmit, and correct site deficiencies. |