Inspection Status: Not Ready
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
PDSD Engineering Division Pre-Construction SITE |
|
Not Ready |
|
| 09/07/2022 |
PDSD Engineering Division Pre-Construction SITE |
BBENEDON |
Partial Approval |
Entered by VVERA1 - Partial approval. Jeff Lang w/ Lang construction.
Schedule inspections biweekly for Stormwater. Schedule intermediate inspections daily for below grade piping. Comply with all Water harvesting specifications |
| 04/11/2023 |
PDSD Engineering Division Pre-Construction SITE |
|
Passed |
|