Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP21-0210
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
10/17/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
10/17/2022 | ENGR Grading Final | DROBERTS | Approved | Entered by DROBERT5 - |
11/02/2021 | ENGR Grading Final | BBENEDON | Continued | Entered by NGARCIA3 - Continued. Mike and Arlene called with engineering questions. This is a small residential project. The building pad has been graded at this time. The gate code is #1124 |
10/18/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, NO CONCERNS AT THIS TIME |
05/05/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, CREWS HAVE POURED THE FLOOR SLAB ONLY |
03/15/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - CONTINUED, CONTRACTOR WORKING ON SETTING FORMS AND PERFORMING PLUMBING INSTALLATION |
10/29/2021 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - PARTIAL, THE PAD HAS BEEN DEVELOPED BUT NO OTHER WORK HAS BEEN DONE AT THIS TIME Gate code is #1124 |
10/28/2021 | ENGR Grading Final | IVR USER | Cancelled | Entered by IVR USER - IVRS - RI canceled |