Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP21-0184

Parcel: 108255470


Addresses:

2008 E RIVER RD

Inspection Status: Partial Pass

Inspection History: Consultation SITE

Date Description Inspector Results Comments
06/05/2026 Consultation SITE Partial Pass Contractor wanted to know the process for building a Refuse Enclosure and when inspections should scheduled.
Recap:
Schedule inspection for wall footer to check reinforcing.
Schedule pre-grout inspection when wall is at 4 feet. (1st lift)
Schedule pre-grout inspection is built to top. (2nd lift)
Schedule inspection for Ballard footers for correct spacing
Schedule inspection for floor reinforcing mat- apron can be scheduled at the same time and the Bollard inspection as well.
Final Inspection is when gates are complete, with holes for cane bolts and Enclosure is finished. To check functionality.
06/09/2026 Consultation SITE Partial Pass Okay to pour slab after expansion is installed. Call in for grouting.
06/12/2026 Consultation SITE Passed 6/12/26 - Site visit to observe refuse enclosure wall grout in single lift. Reinforcement is correct. Grout is a good consistency to flow and cells are being vibrated.
07/31/2025 Consultation SITE Not Ready We need to figure out where to start and end.
1) sidewalks are being replaced
2) landscaping needs to be finished.
3) stairs and rails need to be painted.
4) ADA signs need to be installed
5) carport needs to be completed
6) all fencing and construction materials and Conex boxes will need to be removed.