Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 09/29/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. No activity on site at this time, gate is locked. Ongoing progress is evident. Stormwater controls are in place as well as concrete containment. Have been unable to contact superintendent for this project.
635 W Roger Rd
|
| 09/16/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by VVERA1 - Continued. No activity on site at this time, gate is locked.
|
| 10/06/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Contractor on site at this time. Kevin with G and J construction. At 520-490-1274. Please schedule inspections 09150, 09152, and 09154, coordinate inspection when superintendent is on site. Please provide Message when scheduling inspections
651 W ROGER RD |
| 10/06/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued
721 W ROGER RD |
| 10/06/2022 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by NGARCIA3 - Continued. Kevin with G and J construction. At 520-490-1274. Please schedule inspections 09150, 09152, 09154, coordinate inspection when superintendent is on site. Please provide Message when scheduling inspections
635 W ROGER RD |
| 01/26/2024 |
ENGR Grading Final |
|
Partial Pass |
install sidewalk scupper at East portion of new buildings, correct grade around sidewalk scuppers and at grate attachment to Stormwater piping. remove construction debris. Install accessible signage. complete landscaping and basin for final approval. |
| 04/12/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
grading, curbs and sidewalks in progress. Construction debris on site temporary fencing still in place. Kevin with G and J |
| 05/14/2024 |
ENGR Grading Final |
|
Passed |
|
| 06/15/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Courtesy, unscheduled inspection. Final grading for basin underway at this time. Ensure all water harvesting areas are installed as shown. |