Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP21-0167
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
09/16/2022 | ENGR Grading Final | BBENEDON | Approved | Entered by VVERA1 - Approved |
09/06/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - LOOKED AT THE LANDSCAPE ITEMS AND THE TRASH ENCLOSURE. 1) THE ISLANDS ARE NOT DEEP ENOUGH, THEY ARE AT THE SAME ELEVATION AS THE CURB OPENING, ADVISED THE CONTRACTOR THAT THERE NEEDS TO BE 6-9 INCHES OF FREEBOARD SPACE BELOW THE LOWEST POINT OF THE INLET. 2) THE TRASH ENCLOSURE IS TOO SMALL AND WILL NEED TO BE REDONE UNLESS ENVIRONMENTAL SERVICES AGREES IT IS ACCEPTABLE. I SHOW LARRY MCMANUS OF MCMANUS CONSTRUCTION THAT THE PLANS WERE APPROVED WRONG WITH THE WRONG DETAIL AND MAY NEED TO BE REDONE. 3) CREWS ARE WORKING ON PIPE INSTALLATION ON THE NORTH SIDE OF THE SITE, THIS WORK APPEARS TO BE OKAY. I HAVE ADVISED THEM TO CENTER THE PIPE AS THEY BACKFILL IT AND TAKE PHOTOS WHILE DOING THE WORK. |
07/06/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN /SOME OF THE SITE AREA |
06/03/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - LOOKED ATG THE 12 PIPE INSTALLATION ON THE NORTH SIDE OF THE SITE FROM THE EXISTING SERVICE TO THE NEW LOCATION FOR THE STORMWATER SYSTEM. I CONTACTED PHILLIP WITH ADS PIPE IN PHOENIX AND ASKED OBOUT THE REQUIREMENTS FOR THE TRENCHING OF THE PIPE AND THEBACKFILL REQUIREMENTS. THE CONTRACTOR IS GOING TO USE ABC FOR THE BEDDING MATERIAL AND FOR THE FILL MATERIAL UPTO 1 FOOT ABOVE THE PIPE, THEN THEY WILL BE USING THE NATIVE SOILS FROM THE SITE. THEY WILL TAKE PHOTO'S OF THE INSTALLATION AND THE PLACEMENT OF THE ENGINEERED BACKFILL. ONCE THIS WORK IS COMPLETED AND APPROVED BY MYSELF THEY WILL BE WORKING ON THE NATIVE BACKFILL. |
05/24/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN GRADING FOR SIDEWALK . |
04/01/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN CONTRACTOR NOT ON SITE NEED TO RESCHEDULE. |
11/30/2021 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN GRADING THE PAD FOR THE BUILDING. |
09/20/2022 | ENGR Grading Final | MHERNANDEZ | Partial Approval | Entered by NGARCIA3 - PARTIAL |
09/16/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by VVERA1 - Partially approved. Complete previously noted corrections. Provide notice of termination forSWPPP |
07/27/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN/ GOOD TO POUR FOR THE FLOOR FOR TRASH BIN. |
07/26/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN THE FLOOR FOR THE TRASH BIN IS NO READY FOR INSPECTION.RESCHEDULE FOR THURSDAY. |
07/06/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN /THE REBAR LAYOUT IS NONCOMPLIANT .CONTRACTOR WILL TAKE A PHOTO AND SEND IT TO ME AFTER RELAY OUT THE REBAR. |
11/09/2022 | ENGR Grading Final | Passed | N/A | |
11/09/2022 | ENGR Grading Final | Passed | N/A | |
11/09/2022 | ENGR Grading Final | Passed | N/A |