Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | PDSD Site/Engineering Division - Landscaping | Not Ready | ||
10/27/2022 | PDSD Site/Engineering Division - Landscaping | Not Ready | ||
05/08/2024 | PDSD Site/Engineering Division - Landscaping | Partial Pass | Ongoing construction in the common areas and lot areas | |
05/16/2024 | PDSD Site/Engineering Division - Landscaping | Partial Pass | where is construction going on quite a few lots | |
05/22/2024 | PDSD Site/Engineering Division - Landscaping | Partial Pass | contractors has not completed building on all the pads yet there’s more landscaping to be done. | |
06/10/2024 | PDSD Site/Engineering Division - Landscaping | Partial Pass | contractor needs to hydroseed behind the lots on the south west side of the project and address the erosion protection | |
09/23/2024 | PDSD Site/Engineering Division - Landscaping | Partial Pass | The contractor still building on the lot. And all those lots, the landscaping is not completed. On the common areas contractor still has construction equipment on some of the areas that needs to be cleaned up before we can pass this. | |
11/16/2023 | PDSD Site/Engineering Division - Landscaping | Partial Pass | Continue to work in the commons area | |
11/19/2024 | PDSD Site/Engineering Division - Landscaping | Passed | All plants are completed per plan, all dead plants have been replaced. Hydro seed has been completed to spec. |