Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP21-0102

Parcel: 14102020B


Addresses:

10090 E DREXEL RD


Inspection Status: Not Ready

Inspection History: PDSD Site/Engineering Division - Landscaping

Permit Number - DP21-0102

Inspection Description - PDSD Site/Engineering Division - Landscaping

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 PDSD Site/Engineering Division - Landscaping Not Ready
10/27/2022 PDSD Site/Engineering Division - Landscaping Not Ready
PDSD Site/Engineering Division - Landscaping Requested
05/08/2024 PDSD Site/Engineering Division - Landscaping Partial Pass Ongoing construction in the common areas and lot areas
05/16/2024 PDSD Site/Engineering Division - Landscaping Partial Pass where is construction going on quite a few lots
05/22/2024 PDSD Site/Engineering Division - Landscaping Partial Pass contractors has not completed building on all the pads yet there’s more landscaping to be done.
06/10/2024 PDSD Site/Engineering Division - Landscaping Partial Pass contractor needs to hydroseed behind the lots on the south west side of the project and address the erosion protection
09/23/2024 PDSD Site/Engineering Division - Landscaping Partial Pass The contractor still building on the lot. And all those lots, the landscaping is not completed. On the common areas contractor still has construction equipment on some of the areas that needs to be cleaned up before we can pass this.
11/16/2023 PDSD Site/Engineering Division - Landscaping Partial Pass Continue to work in the commons area