Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: SITE - Stormwater Setup and Controls
| Date |
Description |
Inspector |
Results |
Comments |
| 04/22/2022 |
SITE - Stormwater Setup and Controls |
DROBERTS |
Approved |
Entered by NGARCIA3 - APPROVED
1102 E 36TH ST |
| 04/22/2022 |
SITE - Stormwater Setup and Controls |
DROBERTS |
Approved |
Entered by NGARCIA3 - APPROVED
1002 E 36TH ST |
| 04/21/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN NO CONCERNS AT IS TIME.
1102 E 36TH ST
|
| 04/21/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN NO CONCERNS AT IS TIME.
1002 E 36TH ST
|
| 04/01/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN PLACING 12” AND 18 “ STORM DRAIN PIPE.NORTH WEST OFF OF 36TH ST. |
| 03/30/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN. NO CONCERNS AT IS TIME. |
| 03/22/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /INSTALLING 18” STORM DRAIN PIPE. |
| 03/17/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /INSTALLING 30 N 18" PIPE.
1102 E 36TH ST |
| 03/17/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /INSTALLING 30 N 18" PIPE.
1002 E 36TH ST |
| 03/01/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN/ INSTALLING 18” DRAINAGE . GOOD AND NO CONCERNS .
1102 E 36TH ST |
| 03/01/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN/ INSTALLING 18” DRAINAGE . GOOD AND NO CONCERNS .
1002 E 36TH ST |
| 02/24/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - INSTALLED 300 LF. OF 42” PIPE. THE SOUTH EAST CORNER OF THE PROJECT. |
| 02/09/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /INSTALLING 42” DRAINAGE PIPE.SOUTHEAST OF PROJECT.
|
| 02/01/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN GOOD INSTALLED 6” PIPE. |
| 01/18/2022 |
SITE - Stormwater Setup and Controls |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /LOOKS GOOD AS OF TODAY. |
| 12/01/2023 |
SITE - Stormwater Setup and Controls |
|
Passed |
|