Permit: DP21-0076

Parcel: 103192850

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/05/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - continued. Grading activities
09/15/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Grading
07/28/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Water mains installation
07/14/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Utility work in progress. Material piles on site cul-de-sac has been graded
07/12/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continue. Utility work
07/06/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Water utility work in progress. On site, John with Mattamy homes
06/30/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Water utility work in progress
06/21/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continue. Sewer and electrical utilities
06/17/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Water and sewer utility work in progress. Material piles and debris piles throughout the site
06/10/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Water utility work
06/01/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Sewer utility work in progress
05/27/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Utility work electrical
05/17/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Sewer utility work started
05/06/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Material stock piles on site no activity at this time
04/22/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Material deliveries and stockpile
04/19/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Utility work
04/13/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Material stock piles
04/05/2022 ENGR Grading Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. Rough grading
03/31/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. No activity on site today
03/09/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Utility work starting
03/02/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Material importing and pad buildup.
02/03/2022 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Material importing.
01/25/2022 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Material importing and grading
01/13/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Courtesy unscheduled inspection for Chip with dirt works. Material importing in progress. Chip now has a copy of the permit and will schedule inspections on a regular basis.
12/22/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Dirtworks contracting, Grading activities
12/14/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Rough grading operations in progress
11/30/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued . Rough grading in progress.
11/24/2021 ENGR Grading Final BBENEDON Continued Entered by RSALDAT1 - Continued. Rough Grading in progress
11/19/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Grading operations in progress. Tree relocating in progress, arbor tree in cactus at 300 -0045.
11/16/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. No activity on site at this time
11/10/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Unscheduled inspection directed by Dave Roberts. Permit has been issued, however without the required inspection codes. Please add all development package engineering inspection codes. Chip with dirt works 237-7522. Provide NOI. Provide address signage.
11/09/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Removal of vegetation piles in progress.
11/04/2021 ENGR Grading Final BBENEDON Continued Entered by NGARCIA3 - Continued. Site has been partially cleared. Debris piles on site. Track out protection has been installed.
11/03/2021 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Tentative plat at Westbridge at Silver Bell. Chip with Dirtworks 237-7522. Plan has been approved but not yet issued. Contractor clearing growing and transplanting seven trees. Provide state NOI and proper signage Schedule preconstruction meeting with issuance of permit
07/18/2024 ENGR Grading Final Passed