Inspection History Details
Inspection Status: Not Ready
Inspection History: SITE - Stormwater Setup and Controls
Permit Number - DP21-0073
Inspection Description - SITE - Stormwater Setup and Controls
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | SITE - Stormwater Setup and Controls | Not Ready | ||
01/10/2024 | SITE - Stormwater Setup and Controls | Partial Pass | contractors good to pour the footer for the HEADWALL on the east side of the project closest to Wilmont | |
01/17/2024 | SITE - Stormwater Setup and Controls | Partial Pass | This inspection was completed on January 17th, it was for a headwall inspection just west of Wilmot on the north side of the street. A partial pass was done as a storm water and control inspection as there was nothing in the system for them to use for this. | |
03/12/2024 | SITE - Stormwater Setup and Controls | Partial Pass | ||
03/26/2024 | SITE - Stormwater Setup and Controls | Partial Pass | Picture taken of area for slurry pour. Will return on 3/27/24 to retake and look after pour is completed. | |
06/08/2023 | SITE - Stormwater Setup and Controls | Partial Pass | No concerns at this time | |
06/21/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | Contractor is installing 42 inch RCP’s. The trench is not Wide enough. Contractor does not have a set of plans or a set of cut sheets on site. Until he gets a set of plans or a set of cut sheets. He can continue. | |
07/17/2023 | SITE - Stormwater Setup and Controls | Complete (Recurring) | No concerns at this time | |
10/09/2023 | SITE - Stormwater Setup and Controls | Not Ready | In process | |
12/21/2022 | SITE - Stormwater Setup and Controls | Complete (Recurring) | No concerns at this time |