Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 06/23/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN / THERE IS NO WATTLES OR TRENCH AND BERM IN PLACE YET.
INFORMED THE CONTRACTOR TO CALL IN FOR INSPECTION EVERY TWO WEEKS. |
| 04/13/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /NOT IN PLACE YET. |
| 03/13/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
|
| 03/27/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Storm water pipeline phase 2 good to continue. |
| 08/06/2024 |
SITE - Stormwater Follow-up
|
|
Complete (Recurring) |
Both large basins are holding water well past the 24 hr mark. Billy is working with civil to come up with a fix for these issues. |
| 10/09/2023 |
SITE - Stormwater Follow-up
|
|
Not Ready |
|