Inspection Status: Complete (Recurring)
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 06/13/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN / CONTRACTOR FORMED AND POURED THE MANHOLE WITH OUT INSPECTIONS .CONTRACTOR NEED THE ENGINEER OF RECORD TO CERTIFIED THE POUR AND THE FORMS.
|
| 05/12/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by RSALDAT1 - CN /INSTALLING 42” SRP GOING NORTH .GOOD AS OF TODAY. |
| 05/05/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /NO CONCERNS AT IS TIME |
| 05/02/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN / INSTALLING 48” S R P ON THE NORTH END OF THE BUILDING. |
| 04/13/2022 |
SITE - Stormwater Follow-up
|
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN |