Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 07/27/2022 | ENGR Grading Final | BBENEDON | Continued | Entered by VVERA1 - Continued. Electrical utility installations in progress. Building foundation work in progress. Material piles present. Site premature fencing installed. No stormwater controls, no address, no signage posted. Site locked up at 1 PM. No activity at this time no job trailer on site. Gate locked |
| 08/11/2022 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by NGARCIA3 - Not ready. Reschedule for trash enclosure footings. |
| 07/27/2022 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by VVERA1 - Not ready. Site is locked, there is no access. No contact information was provided. |
| 09/13/2022 | ENGR Grading Final | BBENEDON | Partial Approval | Entered by NGARCIA3 - Partially approved. 4 inch SDR 35 rain drains. |
| 07/27/2022 | ENGR Grading Final | BBENEDON | Not ready for Inspection | Entered by VVERA1 - Not ready. Site is locked, there is no access. No contact information was provided. |
| 01/10/2023 | ENGR Grading Final | Complete (Recurring) | ||
| 01/10/2023 | ENGR Grading Final | Complete (Recurring) | ||
| 01/24/2024 | ENGR Grading Final | Partial Pass | building construction in progress. No activity on site, raining | |
| 04/11/2023 | ENGR Grading Final | Complete (Recurring) | ||
| 04/28/2023 | ENGR Grading Final | Not Ready | Accessible parking is non-compliant, slopes exceed 2%. Provide traffic rated utility covers in parking lot. Provide pedestrian rated utility covers in pedestrian walkways; tripping hazard present due to broken utility cover. Trash enclosure built without inspections, and is not built to specifications shown on approved drawings. project is on going at this time. Complete all work as shown. Correct tripping hazard and accessible parking for partial approval. |
|
| 05/02/2024 | ENGR Grading Final | Passed | Redundant Inspection | |
| 05/24/2023 | ENGR Grading Final | Partial Pass | See previously noted corrections. On-site meeting with Zach. Telephone conversation with Wayne Swan. | |
| 05/24/2023 | ENGR Grading Final | Partial Pass | See previously noted corrections. On-site meeting with Zach. Telephone conversation with Wayne Swan. | |
| 06/28/2023 | ENGR Grading Final | Complete (Recurring) | Building construction in progress. Work area contained within temporary fencing. | |
| 11/15/2023 | ENGR Grading Final | Partial Pass | ||
| 12/14/2022 | ENGR Grading Final | Not Ready | Crews working on installing and pouring concrete curbs on site north sidewalks for main buildings Has been poured will need to be checked for ADA compliant. Form set up for concrete curb appear to be OK but they soil underneath the curb has not been compacted so this shouldn’t be poured upon well let the engineer of record now. The trash enclosure Pad has been constructed incorrectlyThe vertical rebar’s for the walls are not in the footers no other work should happen on this trashing closure without further discussion. The two eastern buildings have been constructed sidewalks have been formed in between the buildings no scuppers I’ve been noted in the area to take care of the rain water from the roof drains coming out the side of the building. | |
| 12/14/2022 | ENGR Grading Final | Not Ready | Crews working on installing and pouring concrete curbs on site north sidewalks for main buildings Has been poured will need to be checked for ADA compliant. Form set up for concrete curb appear to be OK but they soil underneath the curb has not been compacted so this shouldn’t be poured upon well let the engineer of record now. The trash enclosure Pad has been constructed incorrectlyThe vertical rebar’s for the walls are not in the footers no other work should happen on this trashing closure without further discussion. The two eastern buildings have been constructed sidewalks have been formed in between the buildings no scuppers I’ve been noted in the area to take care of the rain water from the roof drains coming out the side of the building. |