Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP21-0038

Parcel: 107130800


Addresses:

263 W GLENN ST

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
07/27/2022 ENGR Grading Final BBENEDON Continued Entered by VVERA1 - Continued. Electrical utility installations in progress. Building foundation work in progress. Material piles present. Site premature fencing installed. No stormwater controls, no address, no signage posted. Site locked up at 1 PM. No activity at this time no job trailer on site. Gate locked
08/11/2022 ENGR Grading Final BBENEDON Not ready for Inspection Entered by NGARCIA3 - Not ready. Reschedule for trash enclosure footings.
07/27/2022 ENGR Grading Final BBENEDON Not ready for Inspection Entered by VVERA1 - Not ready. Site is locked, there is no access. No contact information was provided.
09/13/2022 ENGR Grading Final BBENEDON Partial Approval Entered by NGARCIA3 - Partially approved. 4 inch SDR 35 rain drains.
07/27/2022 ENGR Grading Final BBENEDON Not ready for Inspection Entered by VVERA1 - Not ready. Site is locked, there is no access. No contact information was provided.
01/10/2023 ENGR Grading Final Complete (Recurring)
01/10/2023 ENGR Grading Final Complete (Recurring)
01/24/2024 ENGR Grading Final Partial Pass building construction in progress. No activity on site, raining
04/11/2023 ENGR Grading Final Complete (Recurring)
04/28/2023 ENGR Grading Final Not Ready Accessible parking is non-compliant, slopes exceed 2%. Provide traffic rated utility covers in parking lot. Provide pedestrian rated utility covers in pedestrian walkways; tripping hazard present due to broken utility cover.
Trash enclosure built without inspections, and is not built to specifications shown on approved drawings.
project is on going at this time.
Complete all work as shown.
Correct tripping hazard and accessible parking for partial approval.
05/02/2024 ENGR Grading Final Passed Redundant Inspection
05/24/2023 ENGR Grading Final Partial Pass See previously noted corrections. On-site meeting with Zach. Telephone conversation with Wayne Swan.
05/24/2023 ENGR Grading Final Partial Pass See previously noted corrections. On-site meeting with Zach. Telephone conversation with Wayne Swan.
06/28/2023 ENGR Grading Final Complete (Recurring) Building construction in progress. Work area contained within temporary fencing.
11/15/2023 ENGR Grading Final Partial Pass
12/14/2022 ENGR Grading Final Not Ready Crews working on installing and pouring concrete curbs on site north sidewalks for main buildings Has been poured will need to be checked for ADA compliant. Form set up for concrete curb appear to be OK but they soil underneath the curb has not been compacted so this shouldn’t be poured upon well let the engineer of record now. The trash enclosure Pad has been constructed incorrectlyThe vertical rebar’s for the walls are not in the footers no other work should happen on this trashing closure without further discussion. The two eastern buildings have been constructed sidewalks have been formed in between the buildings no scuppers I’ve been noted in the area to take care of the rain water from the roof drains coming out the side of the building.
12/14/2022 ENGR Grading Final Not Ready Crews working on installing and pouring concrete curbs on site north sidewalks for main buildings Has been poured will need to be checked for ADA compliant. Form set up for concrete curb appear to be OK but they soil underneath the curb has not been compacted so this shouldn’t be poured upon well let the engineer of record now. The trash enclosure Pad has been constructed incorrectlyThe vertical rebar’s for the walls are not in the footers no other work should happen on this trashing closure without further discussion. The two eastern buildings have been constructed sidewalks have been formed in between the buildings no scuppers I’ve been noted in the area to take care of the rain water from the roof drains coming out the side of the building.