Permit: DP21-0014

Parcel: 136301380

Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Date Description Inspector Results Comments
02/10/2026 ENGR - Drainage Structures Partial Pass 2/10/26
Channel next to lot 27 Has footer dug out for 8" header 12" deep. Okay to pour this header. Backfill a compact behind header.
The area at the end of the lots to the right hand side of channel is also correct to pour the header and place grouted riprap.
The slope behind lot 27 is in process to place mirafi fabric and hand placed rip rap. The is being done correct.
Channel has had sediment cleaned out.
02/17/2026 ENGR - Drainage Structures Passed 2/17/26
All corrections have been made detailed in the Email sent Nov 19th except Sediment marker is still not installed in Basin D-1. This needs to be installed per detail U/13 in the DP plans.