10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/14/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by NGARCIA3 - IS CONTINUED, MOST OF THE SITE WORK IS BEING WATCHED BY TDOT, HOSES ARE BEING CONSTRUCTED AT THIS TIME ON THIS SITE. |
05/13/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by VVERA1 - IS PARTIAL, CREWS WORKING ON NEEDED SITE WORK AS NEEDED FOR A FULL C OF O. |
04/01/2022 | ENGR Grading Final | DROBERTS | Continued | Entered by VVERA1 - IS CONTINUED, CONTRACTOR WORKING ON FINE GRADING PAD ELEVATIONS, AND INSTALLATION OF UTILITIES. |
01/20/2023 | ENGR Grading Final | Not Ready | Complete all work on the site prior to calling this inspection again for a final approval | |
01/20/2023 | ENGR Grading Final | Not Ready | Complete all work on this site prior to calling this inspection in again for the final | |
01/20/2023 | ENGR Grading Final | Not Ready | Complete the side as shown on the approved plans prior Calling in this site for the final inspection | |
01/20/2023 | ENGR Grading Final | Not Ready | I’ll work on this site prior to calling this inspection in for the final | |
02/06/2023 | ENGR Grading Final | Complete (Recurring) | Contractors grading for the roads and drainage in the back | |
02/06/2023 | ENGR Grading Final | Complete (Recurring) | Contractors grading in the back area of phase 2 for roads and drainage | |
04/26/2024 | ENGR Grading Final | Partial Pass | COMPLETE ALL WORK AS SHOWN ON THE APPROVED PLANS PRIOR TO SCHEDULING THIS INSPECTION | |
05/01/2023 | ENGR Grading Final | Complete (Recurring) | ||
05/01/2023 | ENGR Grading Final | Complete (Recurring) | ||
05/10/2024 | ENGR Grading Final | Not Ready | Complete all work for showing on the approved plans for the site. An inspection of the schedule for the next week to be done to determine a more specific list of items that will need to be completed prior to the final approval of this project. | |
07/01/2024 | ENGR Grading Final | Not Ready | Complete all work as shown on the Approved plans for all sidewalks, driveways, and remove all excess materials from the site. | |
07/01/2024 | ENGR Grading Final | Not Ready | Complete all work as shown on the Approved plans for all sidewalks, driveways, and remove all excess materials from the site. | |
08/04/2023 | ENGR Grading Final | Not Ready | Grading areas within site have been noted, recall inspection when completed per approved plans. | |
09/29/2023 | ENGR Grading Final | Not Ready | Complete the work on this site is showing on the approved plans prior to calling in this inspection for a reinspection | |
09/29/2023 | ENGR Grading Final | Not Ready | Complete this side is shown on the approved plans prior to scheduling this inspection again in the future | |
09/29/2023 | ENGR Grading Final | Not Ready | Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final | |
10/03/2023 | ENGR Grading Final | Not Ready | ||
10/28/2022 | ENGR Grading Final | Partial Pass |