Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP20-0268

Parcel: 141432070

Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP20-0268

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Complete (Recurring)

Date Description Inspector Results Comments
10/14/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED, NO CONCERNS AT THIS TIME
09/30/2022 SITE - Stormwater Follow-up DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, NO CONCERNS AT THIS TIME DURING THIS INSPECTION.
08/05/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME
07/22/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME
06/24/2022 SITE - Stormwater Follow-up BBENEDON Continued Entered by VVERA1 - Continued
05/27/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME, MINOR CLEANUP OF CAMINO BOLEADORAS IS NEEDED ON THE EASTERN HALF BETWEEN WILMOT ROAD AND KOLB ROAD
05/13/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME.
04/01/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME
03/18/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME.
02/18/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED AT THIS TIME, NO CONCERNS
01/06/2023 SITE - Stormwater Follow-up Complete (Recurring)
01/20/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time continue to call this inspection in every two weeks till this project is complete
02/06/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
02/17/2023 SITE - Stormwater Follow-up Complete (Recurring)
03/17/2023 SITE - Stormwater Follow-up Complete (Recurring)
05/01/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
06/23/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
08/04/2023 SITE - Stormwater Follow-up Not Ready Stormwater controls are in place, and slight runoff in various areas on site is noted.
09/01/2023 SITE - Stormwater Follow-up Complete (Recurring) Multiple areas need wattle or existing wattle areas need to be re staked and adjusted.
09/29/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
10/28/2022 SITE - Stormwater Follow-up Re-inspection required
12/09/2022 SITE - Stormwater Follow-up Complete (Recurring)
12/23/2022 SITE - Stormwater Follow-up Complete (Recurring)