Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
Permit Number - DP20-0254
Inspection Description - ENGR Grading Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
10/27/2022 | ENGR Grading Final | Not Ready | ||
02/16/2024 | ENGR Grading Final | Partial Pass | ||
04/10/2023 | ENGR Grading Final | Not Ready | LOOKED AT THE SITE TO SEE WHAT IS HAPPENING, THEY WILL BE WORKING ON THE BOX CULVERT EAST OF THE MAIN SOUTHERN ACCESS. THE CONTRACTOR WILL BE TRYING TO POUR THE TOE-DOWN WALLS ON BOTH ENDS OF THE BOX AND WILL BE POURING THE FLOOR SLAB NEXT WEEK. | |
04/10/2023 | ENGR Grading Final | Not Ready | LOOKED AT THE SITE TO SEE WHAT IS HAPPENING, THEY WILL BE WORKING ON THE BOX CULVERT EAST OF THE MAIN SOUTHERN ACCESS. THE CONTRACTOR WILL BE TRYING TO POUR THE TOE-DOWN WALLS ON BOTH ENDS OF THE BOX AND WILL BE POURING THE FLOOR SLAB NEXT WEEK. | |
06/14/2023 | ENGR Grading Final | Complete (Recurring) | grading and utility work in the southern and eastern portions In progress at this time. | |
11/22/2023 | ENGR Grading Final | Partial Pass | 2nd entrance road into project still not completed and also some lots along this road as well. Once this is completed I can sign off on grading. | |
11/22/2023 | ENGR Grading Final | Partial Pass | See previous comments on grading | |
11/22/2023 | ENGR Grading Final | Partial Pass | See previous notes on garding | |
11/22/2023 | ENGR Grading Final | Passed |