Permit: DP20-0243

Parcel: 14041133A


Addresses:

3550 E CORONA RD


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP20-0243

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
10/29/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
10/29/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
10/29/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
10/29/2021 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
08/26/2021 ENGR Grading Final DROBERTS Partial Approval Entered by DROBERT5 - INSPECTION 09185 GRADING INTERMEDIATE I MET WIT JAMES FRYXELL AND WE WALKED THE SITE TO CHECKED THE AREAS THAT WERE FOUND TO BE NON-COMPLIANT, THEY ARE STIL OUT OF COMPLIANCE. THEY HAVE DISCUSSED REPAIR OPTIONS WITH THEIR SUBCONTRACTOR AND HAVE DETERMINED THE FOLLOWING. THEY WILL HAVE THE OUTER 2 FEET FROM THE WEST SIDE GROUND DOWN THE REQUIRED AMOUNT AND THEN RESURFACE THE SIDEWALK WITH AN EPOXY COAT OF CONCRETE ON ENSURE THERE IS NOT A TRIP HAZARD. THERE APPEARS TO BE APPROXIMATELY 40 PLUS FEET IN THIS AREA BUT THE CONTRACTOR IS PLANNING ON GROUNDING THE AREAS BEFORE AND AFTER TO KEEP ESTHETICALLY PLEASING. THIS SITE WILL BE REINSPECTED PRIOR TO APPROVING THE COMBO PERMIT PARTIALLY FOR TCO FOR OCCUPANCY.
08/18/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - DP20-0243 INSPECTION 09154 STORMWATER FOLLOWUP INSPECTION 09185 GRADING INTERMEDIATE I A CONVERSATION WITH JAMES ABOUT THE INSPECTION AT CORONA AND COUNTRY CLUB .ALL THE SILK AND SAND THAT NEED TO BE REMOVED .JAMES INFORMED ME THAT SOME OF IT WAS REMOVED AND THE STREET SWEEP WAS GOING TO REMOVE THE REST SAND LATER TODAY . I INFORMED JAMES THAT I WOULD BE OUT THERE IN THE MORNING TO INSPECT THE INSPECTION.
06/29/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN/ GRADING THE PARKING LOT ON THE EAST END OF BUILDING AND PART OF THE SOUTHEAST OF THE BUILDING
06/17/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN/ PAVING THE WEST SIDE OF THR BUILDING PARKING LOT.
06/15/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - PAVING THE NORTH END OF THE BUILDING AND SOME OF THE WEST END TOO.
06/11/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED. THE CREWS ARE WORKING ON THE FOLLOWING ITEMS THIS WEEK: PREPARING SUB GRADE FOR FUTURE AC PLACEMENT, POURING CURBS AND SIDEWALKS AT VARIOUS LOCATIONS THROUGHOUT THE SITE, INSTALLING THE LANDSCAPING AT VARIOUS LOCATIONS. I TALKED TO THE CATAMOUNT SUPERVISOR AND DISCUSSED THEIR FUTURE PLANS, THEY WILL DO MORE OF THE SAME AND WILL START LAYING ASPHALT PAVEMENT STARTING NEXT WEEK.
06/10/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN /PLACING A.B.C. ON THE SOUTH END OF THE BUILDING.
06/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
06/02/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/27/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN POURING THE THREE CATCH BASIN’S APRONS THE NORTH OF BUILDING AND POURED THE SIDEWALK SCUPPER FLOOR ONTHE EAST END OF THE BUILDING AND TWO CATCH BASIN
05/26/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/25/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN . GRADING THE WEST PARKING LOT AND FORMING AND POURING THE SIDEWALK WEST SIDE OF THE PARKING LOT
05/24/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN POURED THREE CATCH BASIN THE SOUTH OF THE BUILDING
05/20/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/18/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/14/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CONTINUED, CREW PREPARING TO INSTALL ADDITIONAL HDPE ALONG THE SOUTH SIDE OF THE MAIN BUILDING, THE TRENCH IS DUG AND SHADED BUT NO PIPE AT THIS TIME
05/12/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/11/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/10/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/07/2021 ENGR Grading Final DROBERTS Partial Approval Entered by VLEON1 - PARTIAL AT THIS TIME, CREWS WORKING ON INSTALLING CPP AONG THE SOUTH SIDE OF THE BUILDING FROM THE WEST TO THE EAST.
05/06/2021 ENGR Grading Final MHERNANDEZ Cancelled Entered by VLEON1 -
05/04/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
05/03/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
04/30/2021 ENGR Grading Final DROBERTS Continued Entered by VLEON1 - CREWS WORKING ON FORMING AND POURING CURBS ON THE NORTH AND EAST SIDE OF THIS SITE. THEY ALSO ARE WORKING ON THE INSTALLATION OF THE CHAINLINK FENCE AT VARIOUS LOCATIONS THROUGHOUT THE SITE.
04/29/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CONTINUE, CURB GRADINT
04/19/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN FORMING THE WING WALLS TOP OF THE RCBC STATION WEST END OF CHANNEL.
04/15/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 -
04/06/2021 ENGR Grading Final MHERNANDEZ Continued Entered by VLEON1 - CN MET WITH JAMES FROM CATAMOUNT .INFORM HIM THE WE WOULD LIKE FOR HIM TO SCHEDULE THE INSPECTION WHEN INSTALLING THE STORM DRAIN .
04/05/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN WORKING ON THE RCBC STATION 24 15 to 25 27 cL.