Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP20-0243

Parcel: 14041133A


Addresses:

3550 E CORONA RD


Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP20-0243

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Passed

Date Description Inspector Results Comments
10/29/2021 SITE - Stormwater Follow-up DROBERTS Approved Entered by DROBERT5 -
08/26/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by RSALDAT1 - -UP PLACING RIP RAP AT THE END OF THE CHANNEL .REMOVE THE EXCESS CONCRETE FROM THE IALAND IN THE PARKING LOT.
08/18/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by RSALDAT1 - DP20-0243 INSPECTION 09154 STORMWATER FOLLOWUP INSPECTION 09185 GRADING INTERMEDIATE I A CONVERSATION WITH JAMES ABOUT THE INSPECTION AT CORONA AND COUNTRY CLUB .ALL THE SILK AND SAND THAT NEED TO BE REMOVED .JAMES INFORMED ME THAT SOME OF IT WAS REMOVED AND THE STREET SWEEP WAS GOING TO REMOVE THE REST SAND LATER TODAY . I INFORMED JAMES THAT I WOULD BE OUT THERE IN THE MORNING TO INSPECT THE INSPECTION.
08/11/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VVERA1 - 9154 (STORMWATER FOLLOW-UP INSP) CN / STORMWATER IS WORKING PROPERLY.
06/29/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by RSALDAT1 - CN /WORKING ON THE BASIN WEST OF THE BUILDING
06/17/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
06/15/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN THE STORMWATER LOOKS GOOD
06/11/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by VLEON1 - CONTINUE NO CONCERNS AT THIS TIME
06/10/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
06/03/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN SETTING THE REBAR FOR THE SCUPPER EAST SIDE OF THE MAIN BUILDING. THERE IS A RFI FOR THE SCUPPER AT STATION 0 35 .CONTRACTOR WILL SUBMIT TO THE CITY OF TUCSON.
06/02/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN FORMING FOR THE TWO APRONS FOR CATCH BASIN.
05/27/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
05/26/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN /CATCH BASIN NEED TO BE CLEANED OUT . BEFORE POURING.
05/24/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
05/20/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN /FORMING FOR CATCH BASIN THE SOUTH SIDE OF THE BUILDING
05/18/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN / ONE OF THE CONTRACTOR HIT 48” STORMWATER LINE .NEED TI BE REPAIRED .IHAVE PHOTOS .
05/14/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME
05/12/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN / INSTALLING THE 48” STORM DRAIN PIPE.AND BACKFILLING.AS THEY GO.
05/11/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 -
05/10/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN I INFORMED THE CONTRACTOR CATAMOUNT ABOUT HAVE ONE OF THE SUBCONTRACTOR GOING INTO THE MANHOLE WITHOUT CONFINED SPACE EQUIPMENT ON.
05/07/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME, MINOR TRACK OUT NOTED, SWEEPERS SET TO CLEANUP LATER TODAY.
05/06/2021 SITE - Stormwater Follow-up MHERNANDEZ Cancelled Entered by VLEON1 -
05/04/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CONTINUE - POURED THE SCUPPER AND THE CATCH BASIN
05/03/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - FORMING CATCH BASINS AND SCUPPER ON THE NORTH END OF BUILDING
04/30/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by VLEON1 - NO CONCERNS AT THIS TIME
04/29/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CONTINUE BACKFILLING THE RCBC
04/28/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN BACKFILLING THE 10” STORM DRAIN PIPE. PLACING 24” CONCRETE CURB THE WEST END OF BUILDING.
04/26/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN. / BACKFILLING THE 30” STORM DRAIN PIPE NORTHWEST OF BUILDING POURING THE RCBC TOP OF BOX WEST END OF CHANNEL.
04/23/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by VLEON1 - CONTINUED AT THIS TIME, THERE WERE NO CONCERNS NOTED DURING THE INSPECTION ON THIS DATE.
04/21/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CONTINUE POURED FOUR MANHOLE NORTH OF BUILDING
04/21/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN POURD TWO MANHOLE.NORTH OF BUILDING .
04/20/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN BACKFILLING THE HDPE STORM DRAIN NORTH SIDE OF BUILDING.
04/19/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN INSTALLING 30” storm drain
04/15/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - CN INSTALLING THE STORM DRAINAGE PIPE.NORTHWEST OF BUILING
04/14/2021 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VLEON1 - STARTED PLACING STORM DRAIN PIPE ONTHE NORTHWEST SIDE OF THE BUILDING .