Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP20-0243
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/29/2021 | SITE - Stormwater Follow-up | DROBERTS | Approved | Entered by DROBERT5 - |
08/26/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by RSALDAT1 - -UP PLACING RIP RAP AT THE END OF THE CHANNEL .REMOVE THE EXCESS CONCRETE FROM THE IALAND IN THE PARKING LOT. |
08/18/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by RSALDAT1 - DP20-0243 INSPECTION 09154 STORMWATER FOLLOWUP INSPECTION 09185 GRADING INTERMEDIATE I A CONVERSATION WITH JAMES ABOUT THE INSPECTION AT CORONA AND COUNTRY CLUB .ALL THE SILK AND SAND THAT NEED TO BE REMOVED .JAMES INFORMED ME THAT SOME OF IT WAS REMOVED AND THE STREET SWEEP WAS GOING TO REMOVE THE REST SAND LATER TODAY . I INFORMED JAMES THAT I WOULD BE OUT THERE IN THE MORNING TO INSPECT THE INSPECTION. |
08/11/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VVERA1 - 9154 (STORMWATER FOLLOW-UP INSP) CN / STORMWATER IS WORKING PROPERLY. |
06/29/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by RSALDAT1 - CN /WORKING ON THE BASIN WEST OF THE BUILDING |
06/17/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
06/15/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN THE STORMWATER LOOKS GOOD |
06/11/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - CONTINUE NO CONCERNS AT THIS TIME |
06/10/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
06/03/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN SETTING THE REBAR FOR THE SCUPPER EAST SIDE OF THE MAIN BUILDING. THERE IS A RFI FOR THE SCUPPER AT STATION 0 35 .CONTRACTOR WILL SUBMIT TO THE CITY OF TUCSON. |
06/02/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN FORMING FOR THE TWO APRONS FOR CATCH BASIN. |
05/27/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
05/26/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN /CATCH BASIN NEED TO BE CLEANED OUT . BEFORE POURING. |
05/24/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
05/20/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN /FORMING FOR CATCH BASIN THE SOUTH SIDE OF THE BUILDING |
05/18/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN / ONE OF THE CONTRACTOR HIT 48” STORMWATER LINE .NEED TI BE REPAIRED .IHAVE PHOTOS . |
05/14/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME |
05/12/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN / INSTALLING THE 48” STORM DRAIN PIPE.AND BACKFILLING.AS THEY GO. |
05/11/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - |
05/10/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN I INFORMED THE CONTRACTOR CATAMOUNT ABOUT HAVE ONE OF THE SUBCONTRACTOR GOING INTO THE MANHOLE WITHOUT CONFINED SPACE EQUIPMENT ON. |
05/07/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - CONTINUED, NO CONCERNS AT THIS TIME, MINOR TRACK OUT NOTED, SWEEPERS SET TO CLEANUP LATER TODAY. |
05/06/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Cancelled | Entered by VLEON1 - |
05/04/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE - POURED THE SCUPPER AND THE CATCH BASIN |
05/03/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - FORMING CATCH BASINS AND SCUPPER ON THE NORTH END OF BUILDING |
04/30/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - NO CONCERNS AT THIS TIME |
04/29/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE BACKFILLING THE RCBC |
04/28/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN BACKFILLING THE 10” STORM DRAIN PIPE. PLACING 24” CONCRETE CURB THE WEST END OF BUILDING. |
04/26/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN. / BACKFILLING THE 30” STORM DRAIN PIPE NORTHWEST OF BUILDING POURING THE RCBC TOP OF BOX WEST END OF CHANNEL. |
04/23/2021 | SITE - Stormwater Follow-up | DROBERTS | Continued | Entered by VLEON1 - CONTINUED AT THIS TIME, THERE WERE NO CONCERNS NOTED DURING THE INSPECTION ON THIS DATE. |
04/21/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CONTINUE POURED FOUR MANHOLE NORTH OF BUILDING |
04/21/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN POURD TWO MANHOLE.NORTH OF BUILDING . |
04/20/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN BACKFILLING THE HDPE STORM DRAIN NORTH SIDE OF BUILDING. |
04/19/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN INSTALLING 30” storm drain |
04/15/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - CN INSTALLING THE STORM DRAINAGE PIPE.NORTHWEST OF BUILING |
04/14/2021 | SITE - Stormwater Follow-up | MHERNANDEZ | Continued | Entered by VLEON1 - STARTED PLACING STORM DRAIN PIPE ONTHE NORTHWEST SIDE OF THE BUILDING . |