Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 03/07/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN/ NO CHANGES AS OF TODAY GOOD.
1725 E TUCSON MARKETPLACE BL
|
| 03/07/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN/ NO CHANGES AS OF TODAY GOOD.
1705 E TUCSON MARKETPLACE BL
|
| 02/15/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
1725 E TUCSON MARKETPLACE BL |
| 02/15/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN
1705 E TUCSON MARKETPLACE BL |
| 08/12/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - IS PARTIAL, OK TO POUR TRASH ENCLOSURE GROUT
1725 E TUCSON MARKETPLACE BL |
| 08/12/2022 |
ENGR Grading Final |
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - IS PARTIAL, OK TO POUR TRASH ENCLOSURE GROUT
1705 E TUCSON MARKETPLACE BL |
| 03/10/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN/ REBAR FOR POLE FOUNDATION. |
| 02/15/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /SETTING REBAR FOE TRASH BIN GOOD
1725 E TUCSON MARKETPLACE BL |
| 02/15/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /SETTING REBAR FOE TRASH BIN GOOD
1705 E TUCSON MARKETPLACE BL
|
| 03/03/2023 |
ENGR Grading Final |
|
Partial Pass |
Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 |
| 03/03/2023 |
ENGR Grading Final |
|
Partial Pass |
Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 |
| 03/03/2023 |
ENGR Grading Final |
|
Partial Pass |
Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 |
| 03/14/2023 |
ENGR Grading Final |
|
Passed |
Complete all comments as previously discussed and complete the work as needed time to reschedule this inspection |
| 03/14/2023 |
ENGR Grading Final |
|
Passed |
N/A |
| 03/14/2023 |
ENGR Grading Final |
|
Passed |
N/N |
| 11/15/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Grading the parking lot and the road around the hotel |
| 11/29/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Grading the parking lot with rap AB |
| 11/29/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Grading the parking lot with rap AB |
| 11/29/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Grading the parking lot with Rapp AB |
| 12/06/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Good to pour the floor for the trash enclosure and the footing for the screen walls the south end of the building |
| 12/06/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Good to pour the floor for the trash enclosure and the screen wall footers on the south end of the building |
| 12/07/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Placing rebar in the footage around the swimming pool |
| 12/28/2022 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractors good to grout the walls around the swimming pool contractor also is looking for a TC of all but not quite ready for it yet or reschedule for tomorrow or Thursday |
| 12/29/2022 |
ENGR Grading Final |
|
Complete (Recurring) |