| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 10/27/2022 | ENGR Grading Final | Not Ready | ||
| 03/07/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN/ NO CHANGES AS OF TODAY GOOD. 1725 E TUCSON MARKETPLACE BL |
| 03/07/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN/ NO CHANGES AS OF TODAY GOOD. 1705 E TUCSON MARKETPLACE BL |
| 02/15/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN 1725 E TUCSON MARKETPLACE BL |
| 02/15/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN 1705 E TUCSON MARKETPLACE BL |
| 08/12/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL, OK TO POUR TRASH ENCLOSURE GROUT 1725 E TUCSON MARKETPLACE BL |
| 08/12/2022 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by NGARCIA3 - IS PARTIAL, OK TO POUR TRASH ENCLOSURE GROUT 1705 E TUCSON MARKETPLACE BL |
| 03/10/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by VVERA1 - CN/ REBAR FOR POLE FOUNDATION. |
| 02/15/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN /SETTING REBAR FOE TRASH BIN GOOD 1725 E TUCSON MARKETPLACE BL |
| 02/15/2022 | ENGR Grading Final | MHERNANDEZ | Continued | Entered by NGARCIA3 - CN /SETTING REBAR FOE TRASH BIN GOOD 1705 E TUCSON MARKETPLACE BL |
| 03/03/2023 | ENGR Grading Final | Partial Pass | Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 | |
| 03/03/2023 | ENGR Grading Final | Partial Pass | Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 | |
| 03/03/2023 | ENGR Grading Final | Partial Pass | Rein-spection required for all Grading Inspections for the Final for this site, These will be performed week 3/6 to 3/11 | |
| 03/14/2023 | ENGR Grading Final | Passed | Complete all comments as previously discussed and complete the work as needed time to reschedule this inspection | |
| 03/14/2023 | ENGR Grading Final | Passed | N/A | |
| 03/14/2023 | ENGR Grading Final | Passed | N/N | |
| 11/15/2022 | ENGR Grading Final | Complete (Recurring) | Grading the parking lot and the road around the hotel | |
| 11/29/2022 | ENGR Grading Final | Complete (Recurring) | Grading the parking lot with rap AB | |
| 11/29/2022 | ENGR Grading Final | Complete (Recurring) | Grading the parking lot with rap AB | |
| 11/29/2022 | ENGR Grading Final | Complete (Recurring) | Grading the parking lot with Rapp AB | |
| 12/06/2022 | ENGR Grading Final | Complete (Recurring) | Good to pour the floor for the trash enclosure and the footing for the screen walls the south end of the building | |
| 12/06/2022 | ENGR Grading Final | Complete (Recurring) | Good to pour the floor for the trash enclosure and the screen wall footers on the south end of the building | |
| 12/07/2022 | ENGR Grading Final | Complete (Recurring) | Placing rebar in the footage around the swimming pool | |
| 12/28/2022 | ENGR Grading Final | Complete (Recurring) | Contractors good to grout the walls around the swimming pool contractor also is looking for a TC of all but not quite ready for it yet or reschedule for tomorrow or Thursday | |
| 12/29/2022 | ENGR Grading Final | Complete (Recurring) | They called in for the grouting for the enclosure trash enclosure which was approved yesterday by me |