Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 10/27/2022 | ENGR Engineering Final | Not Ready | ||
| 01/20/2023 | ENGR Engineering Final | Not Ready | Complete all work is shown on the approved plans prior to calling the sand for a final inspection | |
| 01/20/2023 | ENGR Engineering Final | Not Ready | Complete all work on this site according to the approved plans prior to calling this in for a final inspection | |
| 05/01/2023 | ENGR Engineering Final | Not Ready | Contractor needs to finish per plan before submitting for finals | |
| 05/01/2023 | ENGR Engineering Final | Not Ready | Need to complete per plan before submitting for final | |
| 09/01/2023 | ENGR Engineering Final | Not Ready | Site needs general trash pick up thru out site and dirt runoff from pad to street in multiple areas thru out site needs to be addressed. |
|
| 09/29/2023 | ENGR Engineering Final | Not Ready | Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final | |
| 09/29/2023 | ENGR Engineering Final | Not Ready | Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final | |
| 10/27/2023 | ENGR Engineering Final | Passed | ||
| 10/27/2023 | ENGR Engineering Final | Passed |