Inspection Status: Complete (Recurring)

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP20-0194

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Complete (Recurring)

Date Description Inspector Results Comments
10/14/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED, NO CONCERNS AT THIS TIME
09/30/2022 SITE - Stormwater Follow-up DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, NO CONCERNS AT THIS TIME DURING THIS INSPECTION.
08/05/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME
07/22/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - ) IS CONTINUED, NO CONCERNS AT THIS TIME
06/24/2022 SITE - Stormwater Follow-up BBENEDON Continued Entered by VVERA1 - Continued
06/13/2022 SITE - Stormwater Follow-up MHERNANDEZ Continued Entered by VVERA1 - CN basin under construction.
05/27/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME, MINOR CLEANUP OF CAMINO BOLEADORAS IS NEEDED ON THE EASTERN HALF BETWEEN WILMOT ROAD AND KOLB ROAD
05/13/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by NGARCIA3 - CONTINUED, NO CONCERNS AT THIS TIME. 6760 E CAMINO BOLEADORAS
04/01/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME
03/18/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME. THIS SITE WILL BE SCHEDULED IN THE FUTURE FOR LANDSCAPING AND THE FINAL GRADING INSPECTIONS.
02/18/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by NGARCIA3 - IS CONTINUED AT THIS TIME, NO CONCERNS
02/04/2022 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - S CONTINUED, NO CONCERNS AT THIS TIME.
12/10/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME. MINOR TRACK OUT NOTED IN THE LOCAL STREETS AFTER LAST NIGHTS RAIN.
11/15/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CN LOOKS GOOD TODAY NOT READY FOR LANDSCAPE INSPECTION YET
10/29/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME.
10/15/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued
10/01/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED AT THIS TIME. MINOR TRACK OUT NOTED ON THE LOCAL STREETS WITHIN THE SUBDIVISION, BUT NOTHING BEING TRANSFERRED OFF SITE.
09/17/2021 SITE - Stormwater Follow-up BBENEDON Continued Entered by RSALDAT1 - Continued.
08/06/2021 SITE - Stormwater Follow-up DROBERTS Continued Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME
01/06/2023 SITE - Stormwater Follow-up Complete (Recurring)
01/20/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns on this site at this time
02/02/2024 SITE - Stormwater Follow-up Complete (Recurring) All set up and controls are in place, no concerns at this time.
02/06/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
02/17/2023 SITE - Stormwater Follow-up Complete (Recurring)
03/17/2023 SITE - Stormwater Follow-up Complete (Recurring)
05/01/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
05/10/2024 SITE - Stormwater Follow-up Complete (Recurring) This site has been inspected for the Stormwater and there are no concerns at this time. This site will be re-inspected next week to verify how close it is to being completed.
06/23/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
08/04/2023 SITE - Stormwater Follow-up Complete (Recurring) Stormwater setup and controls are in place some runoff is visible thru out the site.
09/01/2023 SITE - Stormwater Follow-up Complete (Recurring) Multiple areas on site need runoff cleaned from sidewalk,curb, and street areas.
09/29/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time
10/27/2023 SITE - Stormwater Follow-up Complete (Recurring) No concerns at this time, call an inspection every two weeks through the remainder of the project
10/28/2022 SITE - Stormwater Follow-up Re-inspection required
12/09/2022 SITE - Stormwater Follow-up Complete (Recurring)
12/22/2023 SITE - Stormwater Follow-up Complete (Recurring) Minor cleanup of the sites under construction at this time, general clean of the streets and the basins will be required before the final approval once all work has been completed per the Approved plans.
12/23/2022 SITE - Stormwater Follow-up Complete (Recurring)