Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/18/2022 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by VVERA1 - APPROVED |
| 01/11/2022 |
ENGR Engineering Final
|
MERNANDEZ |
Partial Approval |
Entered by VVERA1 - PARTIAL CONTACT DAVID ROBERTS FOR FINAL
NEED TO MEET WITH DAVID ROBERTS
|
| 09/02/2021 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, FINAL NOT TO BE GIVEN TILL THE ENGINEER OF RECORD HAS SUBMITTED REVISED DRAWINGS FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITE. THESE WILL INCLUDE BUT ARE NOT LIMITED TO: 1) FIRE SERVICE LOCATION HAS BEEN CHANGED FROM THE EAST SIDE OF THE DRIVEWAY TO THE WEST. 2) UNDERGROUND DETENTION BASIN WAS RELOCATED TO THE NORTH PARKING AREA FROM THE WEST PARKING AREA. 3) LONG TERM BICYCLE PARKING WILL BE LOCATED INSIDE THE NORTHERN LOCKED ENCLOSURE AREA.
|
| 09/02/2021 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by NGARCIA3 - APPROVED |
| 04/15/2021 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by VLEON1 - PARTIALLY APPROVED AT THIS TIME, OK FOR A TCO FOR OCCUPANCY. FINAL NOT TO BE GIVEN TILL ALL WORK FOR THIS SITE IS COMPLETED PER THE APPROVED PLANS. |